E Question Help You need to schedule 10 units of product Alpha for delivery in 6

ID: 333921 • Letter: E

Question

E Question Help You need to schedule 10 units of product Alpha for delivery in 6 weeks. Three units of D and 2 units of F are required for each Alpha. The lead time for Alpha is 1 week. Lead time for D is 1 week, and lead time for F is 2 weeks a) Complete the product structure. b) Choose the correct time-phased product structure below O A. B. O C. O D. A. 1 2 3456 Time in weeks 1 2 3 4 5 6 Time in weeks Time in weeks Time in weeks c) Prepare a gross requirements plan for Alpha (enter your responses as whole numbers) Week Required Date Order Release Required Date Order Release Required Date Order Release Click to select your answerts)

Explanation / Answer

A.

As one Alpha requires 3D and 2F

Top blank : Alpha

Left blank: D(3)

Right Blank: F(2)

B.

OPtion D

as per the lead time leading to final completion of A= Alpha

C.