As the production planner for Xiangling Hu? Products, Inc., you have been given a bill of material for a bracket that is made up of a? base, 2 springs?, and 3 clamps. The base is assembled from 1 clamp, and 1 housing. Each clamp has 1 handle and 1 casting. Each housing has 1 bearing, and 2 shafts. There is no inventory on hand.
As the production planner for Xiangling Hu Products, Inc., you have been given a bill of material for a bracket that is made up of a base, 2 springs, and 3 clamps. The base is assembled from 1 clamp and 1 housing. Each clamp has 1 handle and 1 casting. Each housing has 1 bearing and 2 shafts. There is no inventory on hand. a) Design a product structure noting the quantities for each item and show the low-level coding. Match each number in the structure below with the corresponding item. Bracket NumbItem Spring(2) Il Housing(1) Base) II Casting(1) |Shaft(2) Clamp(3) Clamp) Handle) IV HandlepCastingy) b) Determine the gross quantities needed of each item if you are to assemble 50 brackets.Explanation / Answer
Solution :
Part B :
Part C :
Item Quantity On-Hand Net Requirement Gross Requirement Bracket 0 50 50 Base 0 50 50 Spring 0 100 100 Clamp 0 200 200 Housing 0 50 50 Handle 0 200 200 Casting 0 200 200 Bearing 0 50 50 Shaft 0 100 100Related Questions
Hire Me For All Your Tutoring Needs
Integrity-first tutoring: clear explanations, guidance, and feedback.
Drop an Email at
drjack9650@gmail.com
drjack9650@gmail.com
Navigate
Integrity-first tutoring: explanations and feedback only — we do not complete graded work. Learn more.