As the production planner for Xiangling Hu? Products, Inc., you have been given a bill of material for a bracket that is made up of a? base,

22

springss?,

and

44

clamps. The base is assembled from

22

clampss

and

11

housingnothing.

Each clamp has

11

handle and

11

castingnothing.

Each housing has

11

bearingnothing

and

22

shaftss.

There is no inventory on hand.

This exercise contains only parts b and c.

The product structure is as? follows:

BracketBracket

Base Subscript left parenthesis 1 right parenthesisBase(1)

Clamp Subscript left parenthesis 2 right parenthesisClamp(2)

Handle Subscript left parenthesis 1 right parenthesisHandle(1)

Casting Subscript left parenthesis 1 right parenthesisCasting(1)

Spring Subscript left parenthesis 2 right parenthesisSpring(2)

Housing Subscript left parenthesis 1 right parenthesisHousing(1)

Shaft Subscript left parenthesis 2 right parenthesisShaft(2)

Clamp Subscript left parenthesis 4 right parenthesisClamp(4)

Bearing Subscript left parenthesis 1 right parenthesisBearing(1)

Handle Subscript left parenthesis 1 right parenthesisHandle(1)

Casting Subscript left parenthesis 1 right parenthesisCasting(1)

?b) Determine the gross quantities needed of each item if you are to assemble

125125

brackets.

?Base:

nothing

?(enter

number?).

?Spring:

nothing

?(enter

number?).

?Clamp:

nothing

?(enter

number?).

?Housing:

nothing

?(enter

number?).

?Handle:

nothing

?(enter

number?).

?Casting:

nothing

?(enter

number?).

?Bearing:

nothing

?(enter

number?).

?Shaft:

nothing

?(enter

number?).

?c) Compute the net quantities needed if there are

2525

of the base and

100100

of the clamp in stock.

?Base:

nothing

?(enter

number?).

?Spring:

nothing

?(enter

number?).

?Clamp:

nothing

?(enter

number?).

?Housing:

nothing

?(enter

number?).

?Handle:

nothing

?(enter

number?).

?Casting:

nothing

?(enter

number?).

?Bearing:

nothing

?(enter

number?).

?Shaft:

nothing

?(enter

number?).

?Base:

nothing

units

?(enter

your response as a whole

number?).

?Spring:

nothing

units

?(enter

your response as a whole

number?).

?Clamp:

nothing

units

?(enter

your response as a whole

number?).

?Housing:

nothing

units

?(enter

your response as a whole

number?).

?Handle:

nothing

units

?(enter

your response as a whole

number?).

?Casting:

nothing

units

?(enter

your response as a whole

number?).

?Bearing:

nothing

units

?(enter

your response as a whole

number?).

?Shaft:

nothing

units

?(enter

your response as a whole

number?).

Explanation / Answer

As the production planner for Xiangling Hu? Products, Inc., you have been given a bill of material for a bracket that is made up of a? base,

22

springss?,

and

44

clamps. The base is assembled from

22

clampss

and

11

housingnothing.

Each clamp has

11

handle and

11

castingnothing.

Each housing has

11

bearingnothing

and

22

shaftss.

There is no inventory on hand.

This exercise contains only parts b and c.

The product structure is as? follows:

BracketBracket

Base Subscript left parenthesis 1 right parenthesisBase(1)

Clamp Subscript left parenthesis 2 right parenthesisClamp(2)

Handle Subscript left parenthesis 1 right parenthesisHandle(1)

Casting Subscript left parenthesis 1 right parenthesisCasting(1)

Spring Subscript left parenthesis 2 right parenthesisSpring(2)

Housing Subscript left parenthesis 1 right parenthesisHousing(1)

Shaft Subscript left parenthesis 2 right parenthesisShaft(2)

Clamp Subscript left parenthesis 4 right parenthesisClamp(4)

Bearing Subscript left parenthesis 1 right parenthesisBearing(1)

Handle Subscript left parenthesis 1 right parenthesisHandle(1)

Casting Subscript left parenthesis 1 right parenthesisCasting(1)

?b) Determine the gross quantities needed of each item if you are to assemble

125125

brackets.

?Base:

nothing

?(enter

number?).

?Spring:

nothing

?(enter

number?).

?Clamp:

nothing

?(enter

number?).

?Housing:

nothing

?(enter

number?).

?Handle:

nothing

?(enter

number?).

?Casting:

nothing

?(enter

number?).

?Bearing:

nothing

?(enter

number?).

?Shaft:

nothing

?(enter

number?).

?c) Compute the net quantities needed if there are

2525

of the base and

100100

of the clamp in stock.

?Base:

nothing

?(enter

number?).

?Spring:

nothing

?(enter

number?).

?Clamp:

nothing

?(enter

number?).

?Housing:

nothing

?(enter

number?).

?Handle:

nothing

?(enter

number?).

?Casting:

nothing

?(enter

number?).

?Bearing:

nothing

?(enter

number?).

?Shaft:

nothing

?(enter

number?).

?Base:

nothing

units

?(enter

your response as a whole

number?).

?Spring:

nothing

units

?(enter

your response as a whole

number?).

?Clamp:

nothing

units

?(enter

your response as a whole

number?).

?Housing:

nothing

units

?(enter

your response as a whole

number?).

?Handle:

nothing

units

?(enter

your response as a whole

number?).

?Casting:

nothing

units

?(enter

your response as a whole

number?).

?Bearing:

nothing

units

?(enter

your response as a whole

number?).

?Shaft:

nothing

units

?(enter

your response as a whole

number?).

Hire Me For All Your Tutoring Needs
Integrity-first tutoring: clear explanations, guidance, and feedback.
Drop an Email at
drjack9650@gmail.com
Chat Now And Get Quote