ID: 336433 • Letter: I
Question
In a garments factory, a part requires 0.10 hours of labor per unit in Work Center B and 1 hour of setup time. The planned order release (order size) for a week is 2000 units. Which of the following is the capacity requirement for a week at Work Center B? a. 101 b. 151 c. 251 d. 201 In a garments factory, a part requires 0.10 hours of labor per unit in Work Center B and 1 hour of setup time. The planned order release (order size) for a week is 2000 units. Which of the following is the capacity requirement for a week at Work Center B? In a garments factory, a part requires 0.10 hours of labor per unit in Work Center B and 1 hour of setup time. The planned order release (order size) for a week is 2000 units. Which of the following is the capacity requirement for a week at Work Center B? 101 151 251 201 a. 101 b. 151 c. 251 d. 201Explanation / Answer
Capacity requirement of work center B
= Number of units x hours of labor per unit + Setup time
= 2,000 x 0.10 + 1
= 200 + 1
= 201 hours
So, as per above calculations, option d is the correct option
Related Questions
Hire Me For All Your Tutoring Needs
Integrity-first tutoring: clear explanations, guidance, and feedback.
Drop an Email at
drjack9650@gmail.com
drjack9650@gmail.com
Navigate
Integrity-first tutoring: explanations and feedback only — we do not complete graded work. Learn more.