In a garments factory, a part requires 0.10 hours of labor per unit in Work Cent

ID: 336433 • Letter: I

Question

In a garments factory, a part requires 0.10 hours of labor per unit in Work Center B and 1 hour of setup time. The planned order release (order size) for a week is 2000 units. Which of the following is the capacity requirement for a week at Work Center B? a. 101 b. 151 c. 251 d. 201 In a garments factory, a part requires 0.10 hours of labor per unit in Work Center B and 1 hour of setup time. The planned order release (order size) for a week is 2000 units. Which of the following is the capacity requirement for a week at Work Center B? In a garments factory, a part requires 0.10 hours of labor per unit in Work Center B and 1 hour of setup time. The planned order release (order size) for a week is 2000 units. Which of the following is the capacity requirement for a week at Work Center B? 101 151 251 201 a. 101 b. 151 c. 251 d. 201

Explanation / Answer

Capacity requirement of work center B

= Number of units x hours of labor per unit + Setup time

= 2,000 x 0.10 + 1

= 200 + 1

= 201 hours

So, as per above calculations, option d is the correct option