Telluride Tours is currently evaluating two mutually exclusive investments. Afte
ID: 3383771 • Letter: T
Question
Telluride Tours is currently evaluating two mutually exclusive investments. After doing a scenario analysis and applying probabilities to each scenario, it has determined that the investments have the following distributions around the expected NPV.
Several member of the management team have suggested that Project A should be selected because it has a higher potential NPV. Other members have suggested that Project B appears to be more conservative and should be selected. They have asked you to resolve this question.
d) Calculate the probability of a negative NPV for both projects.
e) Which project should be projected?
SHOW ALL WORK
Probability NPV-A NPV-B 15% (-34,000) (-12,750) 20% (-8,500) 2,125 30% 17,000 17,000 20% 42,500 31,875 15% 68,000 46,750Explanation / Answer
d) NPA -A
TOTAL 170000
NEGATIVE NPV = 42500
PROBABILITY = 42500/170000 = 0.25
NPV B
TOTAL NPV = 110500
NEGATIVE NPV = 12750
PROABABILITY = 12750/110500= 0.115
E) NPV B SHOULD BE CHOOSEN AS IN THIS PROBABIILITY OF BEGATIVE NPV IS LESS THEN THE NVP A
Related Questions
drjack9650@gmail.com
Navigate
Integrity-first tutoring: explanations and feedback only — we do not complete graded work. Learn more.