Use the following information to answer questions 27-28. On Hand 200 Forecast Cu
ID: 340129 • Letter: U
Question
Use the following information to answer questions 27-28. On Hand 200 Forecast Customer Orders Master Production Schedule 500 Available-to-Promise Period 6 300 250 300 300 200 200 250 200 250 200 150 250 700 27. What is the available-to-promise in period 4? a. 500 b. 100 c. 200 d. 350 e. none of the above 28. What is the available-to-promise in period 1? 0 none of the above d. a. 700 b. 500 c. 250 e. d. the disaggregate plan e. none of the above 29. The difference between planned production and customer orders is known as a. the master production schedule. b. available-to-promise. c. capable-to-promise. a. labor is usually the most constraining resource for services b. service capacity must be provided at the appropriate place and time c. demand for services is easy to predict d. capacity for services is difficult to predict e. none of the above 30. Which of the following is not a characteristic of aggregate planning for servicExplanation / Answer
27. ATP= ONHAND+SUPLLY-DEMAND
ATP= 700-(200+150)
=350
so the answer will be D.350
28. ATP for period 1= (500+200)-250
= 450
so the answer will be E. None of this
29. The difference between planned production and customer demand is known as (B) Available to promise.
30. A- Labour is usually the most constraining resource of services.
Related Questions
Hire Me For All Your Tutoring Needs
Integrity-first tutoring: clear explanations, guidance, and feedback.
Drop an Email at
drjack9650@gmail.com
drjack9650@gmail.com
Navigate
Integrity-first tutoring: explanations and feedback only — we do not complete graded work. Learn more.