Adirondak Marketing Inc. manufactures two products, A and B. Presently, the comp
ID: 341458 • Letter: A
Question
Adirondak Marketing Inc. manufactures two products, A and B. Presently, the company uses a single plantwide factory overhead rate for allocating overhead to products. However, management is considering moving to a multiple department rate system for allocating overhead.
Calculate the plantwide factory overhead rate for Adirondack Marketing Inc.
a.$2.20 per dlh
b.$14.48 per dlh
c.$5.60 per dlh
d.$24.38 per dlh
Overhead Total
Direct
Labor Hours DLH per Product A B Painting Dept. $253,600 10,400 5 7 Finishing Dept. 65,000 11,600 5 5 Totals $318,600 22,000 10 12
Explanation / Answer
Plantwide factory overhead rate for Adirondack Marketing Inc
= 318600 / 22000
= 14.48 Per dlh
Answer = B) $14.48 per dlh
Overhead TotalDirect
Labor Hours DLH per Product A B Painting Dept. $253,600 10,400 5 7 Finishing Dept. 65,000 11,600 5 5 Totals $318,600 22,000 10 12
Related Questions
Hire Me For All Your Tutoring Needs
Integrity-first tutoring: clear explanations, guidance, and feedback.
Drop an Email at
drjack9650@gmail.com
drjack9650@gmail.com
Navigate
Integrity-first tutoring: explanations and feedback only — we do not complete graded work. Learn more.