Given below are the normal and crashing data and other information for a project
ID: 346343 • Letter: G
Question
Given below are the normal and crashing data and other information for a project. Compute (a) the crash slope (ie crash cost per day) for each activity, (b) the normal project cost, (c) prioritized the list of activities for crashing from best to worst (d) the project cost if it is to be completed 2 days earlier, the best activities to crash, and alternative critical paths, if any, (e) the earliest time the project can be completed, and (f) the least cost of early completion Note: Activities with the same normal and crash durations cannot be crashed Activity Immediate ES LS EF LF Slack Normal Crash Norm Crash Predecessor Time|Time (days) Time (Days) Cost K$Cost K$ 0 06 60 084128 0 451 6 6 12 120 12 1215 15 0 4514151 15 1521 21 0 10 12 38 36 40 20 30 10 20 B. D 50 100 10 E, F 2Explanation / Answer
Ans A and B
C.
D.
For 2 days earlier:
E and F:
So the following provides the earliest :
E. Time = 10 days
F. Cost = 295
Ans A Dec Var Assumed cost Slope Task Pre Start End Time to take Normal T Crash Normal cost Crash cost Per time Crash Cost Crash A 0 6 6 <= 6 >= 2 10 38 7 10 No B 0 4 4 <= 4 >= 4 12 12 0 12 No C 0 4 4 <= 4 >= 2 18 36 9 18 No D A 6 12 6 <= 6 >= 2 20 40 5 20 No E B,D 12 15 3 <= 3 >= 2 30 33 3 30 No F C 4 14 10 <= 10 >= 6 10 50 10 10 No G E,F 15 21 6 <= 6 >= 2 20 100 20 20 No 0 0 0 Finish Ending 21 Total 120 <= Ans B Total cost 120 Deadline 21 Minimize Obj FuncRelated Questions
Hire Me For All Your Tutoring Needs
Integrity-first tutoring: clear explanations, guidance, and feedback.
Drop an Email at
drjack9650@gmail.com
drjack9650@gmail.com
Navigate
Integrity-first tutoring: explanations and feedback only — we do not complete graded work. Learn more.