orites Unio.us-The Best F- a Voeons Mens Watch. Merriam-webster's L.. E Favorites s Spring 2018 IM417-740 20787 Week 8 Midterm Exam 25 swered net requirements, and make a MRP for this product. All lead times are one week ut of 4.00 the ueation week 4. There are 60 Bs, 250 Cs, and 200 Ds as projected available at atd- Given the following product tree, explode, offset, and determine the gross and and the quantities required are shown in the product tree. The master production schedule calls for 500 As to be available in week 5, and 300 As to be available in beginning. The policy for projected available and scheduled receipt is first-come- first use. In the MRP, what is Planned Order Release for Part C in week 2? Select one: A. 350 B. 450 C. 550 D. 650 E. None of them 4) 8

Explanation / Answer

Requirement of A in week 4 = 300

Gross requirement of C = 2*Requirement of A = 2*300 = 600

Quantity in hand of C = 250

Net requirement of C = Gross requirement - Quantity in hand = 600 - 250 = 350

Ans A