Question: Based on the additional details included below, please complete an act

ID: 347074 • Letter: Q

Question

Question: Based on the additional details included below, please complete an activity network diagram in project management that would be useful for planning and tracking the project from beginning to finish. A sample of a network diagram is included after the additional details. Please follow this format.

Additional details:
The course project consists of developing project deliverables for an actual project. You will be working as a project team, sharing responsibility for the various roles. You may develop the project deliverables for a project you are currently working on, one recently completed, or one that you will undertake in the near future.

The subject of our paper is planning a vacation trip to Jamaica.

The people who are going on the vacation trip and involved in the project are:

Project Manager

Sara

Charter

Elizabeth

Work Breakdown Structure

Kelly

Communication Plan

Chelsey

Network Diagram / Schedule

James

Risk Assessment

Kristine

Cost Budget

Sydney

The assumptions for our trip are:

Only the members of our team will be going -- no spouses or children
Each person will have $2,000 to spend on an all-inclusive resort
Travelers will be staying at the all-inclusive resort for 2 weeks (May 12-26)
Flights, taxis, incidentals and other activities should be booked on their own and are outside the scope of this project

Based on the information included below, please complete a network diagram in project management that would be useful for planning and tracking the project from beginning to finish. This diagram represents a project's critical path as well as the scope for the project. A good network diagram will be a clear and concise graphic representation of a project.

_______________________________________________________________

SUMMARY

Purpose

The purpose of this vacation is to rest and relax.

Description

This trip to Jamaica will be two weeks in length and will include lodging at an all-inclusive resort. Airfare and travel expenses are not included in the cost. Additional documentation will assess risk, outline schedule, and break-out costs.

Objective

The objective of this vacation is to have a relaxing, two-week vacation with friends while staying within a total $2000 budget per person.

Vacation Scope

In scope

In scope activities include:

                Lodging for 14 nights at an all-inclusive resort;

Meals and drinks;

Resort activities

Out of Scope

Out of scope activities include:

Airfare to and from Jamaica;

Travel to and from airport and hotel;

Travel during stay;

Additional excursions not included with resort stay;

Off-site food and beverage

Expected Benefits

Reduced stress

Under budget

Funding

Phase 1 – Resort booking: $500 deposit due for lodging

Phase 2 – Resort arrival: $500 due at check-in

Phase 3 – Resort departure: Remaining balance for lodging and additional excursions (if applicable) due upon check-out

Assumptions

All participants will take care of pre-travel medical necessities

All participants will have up to date passports

No participant will have a name change in the time leading up to the trip

All participants will have the proper insurance to cover incident outside of the United States

The resort is a secure, safe place for vacationers

Constraints

Category

Description

Budget

$1000 per person per week

Schedule

Participation must be confirmed six weeks before travel dates

Resources

Airfare and travel expenses to/from Jamaica at the cost of the individual

Airlines during travel are running on-time

Baggage arrives without delay

Each participant will occupy their own room

Other

Participants arrive at the hotel on time

Additional excursions at the expense of the participant


Risks

Identified risks include:

                Montego Bay Mafia issues

                Turmoil and violence in Kingston

                Rick’s Café cliff-diving

Proposed Timeline and Deliverables

February 19: Vacation participation must be confirmed

February 26: Lodging deposit must be made

March 16: All travel must be booked and confirmed

March 31: Check in to flights early

April 1: Travel, Arrive at hotel no later than 6:00 PM

April 2-April 14: RELAX

April 15: Travel, Shuttle departs to airport at 11:00 AM

Approval Requirements

The project manager has the ability to book resort rooms as long as 14 nights does not exceed $2,000 per person.

Reporting Requirements
This charter and subsequent documents will be updated as necessary after class meetings and online discussions. The documents will be updated by the student listed in the “General Information” section of this document.

Example Network Diagram

Project Manager

Sara

Charter

Elizabeth

Work Breakdown Structure

Kelly

Communication Plan

Chelsey

Network Diagram / Schedule

James

Risk Assessment

Kristine

Cost Budget

Sydney

10 A. Excavate 5 days B. Foundation 2 days C. Frame D. Electrical 9 days E. Roof F. Masonry 8 days G. Interior10 days H. Exterior 7 days I. Landscape 5 days 12 days 12 HIEND 5 days STARTA - Critical Path

Explanation / Answer

Proposed Timeline and Deliverables

February 19: Vacation participation must be confirmed (A)

February 26: Lodging deposit must be made (B)

March 16: All travel must be booked and confirmed (C)

March 31: Check in to flights early (D)

April 1: Travel, Arrive at hotel no later than 6:00 PM (E)

April 2-April 14: RELAX (F)

April 15: Travel, Shuttle departs to airport at 11:00 AM (G)

(A)---7(B)------18(C)--------15(D)-------------1(E)------13(F)------1(G)