Chapter 3 – Assignment Best Bicycles Problem Best’s Bicycles manufactures three

ID: 348522 • Letter: C

Question

Chapter 3 – Assignment

Best Bicycles Problem

Best’s Bicycles manufactures three different types of bikes: the Tiny Tike, the Adult Aero, and the Mountain Monger. Given the information in the table, calculate the required capacity for this year’s production. Note that the times are given for assembly lines, so capacity calculations should be in terms of the number of lines necessary. Assume that Best Bicycles operates three shifts, each with 2,000 hours per year.


Determine the total setup time

Determine the total operating time available

Determine the number of assembly lines

Explanation / Answer

Process time required:

Tiny bike: 14,000x8 = 112,000 minutes/year

Adult Aero: 16,000x10= 160,000 minutes/year

Mountain Monger: 19,000x12= 228,000 minutes/year

Total process time: 112,000+160,000+228,000 = 500,000 minutes/year

Setup Time:

Tiny bike: 1,400x50= 70,000

Adult Aero: 1,600x80= 128,000

Mountain Monger: 750x40= 30,400

Total setup time: 70,000+128,000+30,400= 228,400

Total operating time: 2 shifts/day x 2,000hours/shift/year x 60 minutes/hour

= 240,000minutes/year.

Number of assembly lines: INT (Total process time + total setup time)/ (Total operating time) +1

=INT (500,000+228,400)/ 240,000 + 1

=INT (3.04) +1 = 4