identily the choice that best completes the statement or answers the question. Associated with each question is a weight of 2 points Which of the following statements is true of project management? a. b. c. d. 1. It is a simple discipline with a limited scope. It has specific tools which work universally across all kinds of projects. It does not guarantee successes for all projects. Its framework consists solely of project management knowledge areas. 2. Martha works as a project manager at a bank. Due to certain changes in external factors, Martha needs to ew alterations in the tactical goals of her project. In such a scenario, which of the following will best help Martha cope with the change? a. Negotiation c. Motivation b. Project environment knowledge d. Soft skills 3. In the development phase of the project life cycle: a. the project team creates more detailed project plans, a more accurate cost estimate, and a more thorough WBS. b. the project team delivers the required work, and provides performance reports to stakeholders c. managers develop a business case, which describes the need for the project and basic underlyin concepts. d. managers prepare a preliminary or rough cost estimate for the required work. 4. In thephase, the project team creates a definitive or very accurate cost estimate, delivers the require work, and provides performance reports to stakeholders. a. development c. concept b. implementation d. close-out 5. The_ model of a systems development life cycle assumes that requirements will remain stable af they are defined. a. spiral life cycle c. incremental build life cycle b. d. waterfall life cycle RAD life cycle 6. Themodel uses an approach in which developers work with an evolving prototype, using tools s as computer-aided software engineering, joint requirements planning, and joint application design to facil rapid prototyping and code generation. a. incremental build life cycle c. RAD life cycle b. waterfall life cycle d. spiral life cycleExplanation / Answer
Answer 1:- Which of the following statements is true of project management?
Correct Answer:- It does not guarantee successes for all projects.
Answer 2:- Martha works as a project manager at a bank. Due to certain changes in external factors, Martha needs to make a few alterations in the tactical goals of her project. In such a scenario, which of the following will best help Martha cope with the change?
Correct Answer:- Project environment knowledge
Reason:- This will help her to analyze the external factors affecting the project
Answer 3:- In the development phase of the project life cycle:
Correct Answer:- the project team creates more detailed project plans, a more accurate cost estimate, and a more thorough WBS.
Reason:- In the development phase, detailed study of the project plan is done
Answer 4:- In the _____ phase, the project team creates a definitive or very accurate cost estimate, delivers the required work, and provides performance reports to stakeholders.
Correct Answer:- implementation
Answer 5:- The _____ model of a systems development life cycle assumes that requirements will remain stable after they are defined.
Correct Answer:- waterfall life cycle
Answer 6:- The _____ model uses an approach in which developers work with an evolving prototype, using tools such as computer-aided software engineering, joint requirements planning, and joint application design to facilitate rapid prototyping and code generation.
Correct Answer:- RAD life cycle