A multi-level bill of material:
I. Reflects the components through which the product will be manufactured.
II. Is produced by the engineering department.
III. Is a parts list only and does not contain subassemblies.
a. only I is true
b. only II is true
c. only III is true
d. I and II are true
e. I, II and III are true
Which of the following are objectives of an MPS?
I. Maintain the desired level of customer service.
II. Ensure zero inventory at the end of each planning period.
III. Make the best use of material, labor and equipment.
IV. Maintain inventory investment as required.
a. only I is an objective
b. only I and II are objectives
c. only I, II and III are objectives
d. only I, III and IV are objectives
e. only II, III and IV are objectives
In terms of INCREASING level of detail, which is the best sequence of activities?
I. Material requirements planning.
II. Master production scheduling.
III. Aggregate production planning.
a. I, II and III
b. I, III, and II
c. II, III, and I
d. II, I, and III
e. III, II, and I
Explanation / Answer
A multi-level bill of material reflects the components through which the product will be manufactured.A multi-level structure can be illustrated by a tree and are formed as logical groups of parts into subassemblies based on the way the product is assembled .So
a. only I is true
objectives of an MPS are
Maintain the desired level of customer service.
Make the best use of material, labor and equipment.
Maintain inventory investment as required.
So
e. only II, III and IV are objectives
For INCREASING level of detail, The best sequence of activities are
Aggregate production planning.
Master production scheduling.
Material requirements planning.
So
e. III, II, and I
Please provide feedback and Thumbs up Thanks.
Related Questions
drjack9650@gmail.com
Navigate
Integrity-first tutoring: explanations and feedback only — we do not complete graded work. Learn more.