Academic Integrity: tutoring, explanations, and feedback — we don’t complete graded work or submit on a student’s behalf.

ESTION 26 2 workens needed Task 2 2 wonkers needed 3 days Task 3 Start Projecetw

ID: 352663 • Letter: E

Question

ESTION 26 2 workens needed Task 2 2 wonkers needed 3 days Task 3 Start Projecetwokrced niah Prowect 2 days Task 1 worker needed 4 days Task5 1 worker needed 2 days Given this project and the requirement that the number of resources working on a task cannot be less than the number assigned to the task, answer the following question. if the tasks were placed in a serial relationship with Task 1 first and the others in numerical order, on what day would Task 3 be done? a. day 10 O b. day 9 c. day 18 to save oll answers Click Save and Submit to save and submit. Click Save Al Answers

Explanation / Answer

If tasks are arranged serially, task 1 would take day 1 to 5, task 2 will take day 6 to 8 and task 3 would take day 9 to 10. Thus task 3 would be completed on day 10.

Answer- 10 day