QUESTION 11 2 points Save Answer A network diagram is a hierarchical decomposition of the project scope into work elements to be executed to produce the project deliverables. O True O False QUESTION 12 2 pointsSave Answer Specific criteria listed in the RFP should be restated in the proposal to reinforce to the customer that the contractor understands the requirements. True False QUESTION 13 2 pointsSave Answer The total dollar value approach is the ratio of the total dollar value of proposals that the contractor won as a percentage of the total dollar value of all the proposals the contractor submitted to various customers during a specific time period True Falce Click Save and Submit to save and submit. Click Save All Answers to save all answersExplanation / Answer
11. A network diagram is basically a graphical way of representing tasks of the project and highlighting the critical path.
Work Breakdown structure or WBS is the hierarchical decomposition of the project scope or the work to be done by the teams to achieve the project objectives.
Hence, Statement is False.
12. In RFP, anything that is required is actually mandatory. So, it is valuable to restate the requirements in form of mandatory criteria. This highlights the understanding of the requirements.
Hence, the statement is True.
13. There are 2 ways to measure success of a contractor’s proposals –win ratio and total dollar value. Total dollar value is nothing but the total dollar value of the proposals won by the contractor, expressed in percentage form of the total dollar value of all the submitted proposals of that contractor.
Hence, the statement is True.