Academic Integrity: tutoring, explanations, and feedback — we don’t complete graded work or submit on a student’s behalf.

Earned Value Exercise Complete the following problems: (Total 5) please answer a

ID: 3576094 • Letter: E

Question

Earned Value Exercise

Complete the following problems: (Total 5) please answer all questions.

1. The following project is at the end of its first week. Find the cost and schedule variances, the cost performance index, the schedule performance index and the estimate at completion.

Task

Predecessors

Duration in days

Planned Value ($)

Actual Cost ($)

Percent Complete

A

None

2

500

650

100

B

None

3

1000

1500

100

C

A

2

200

300

50

D

A

5

600

600

20

E

B ,C

6

1200

550

10

To do this exercise, it is best to start with a Gantt chart depicting the task relationships.

CV ______________________     CPI ________________

SV ______________________      SPI ________________

EAC _____________________

2. Using the following information, calculate the cost performance index and the schedule performance index. Then calculate the estimate at c

Planned value: 6700

Earned value: 6100

Actual costs: 7300

Budget at completion: 38900

CPI _______________________                    SPI _____________________________

EAC ______________________

3. The following project is at the end of its third week. Find the cost and schedule variances, the cost performance index, the schedule performance index and the estimate at completion.

Task

Predecessors

Duration in days

Planned Value ($)

Actual Cost ($)

Percent Complete

A

None

3

600

650

100

B

A

5

1000

1500

100

C

A

2

200

300

100

D

A

5

1000

600

100

E

B ,C

6

1200

1200

100

F

C

10

10000

12000

75

G

F

7

700

0

0

H

G

8

1600

0

0

To do this exercise, it is best to start with a Gantt chart depicting the task relationships.

CV ______________________     CPI ________________

SV ______________________      SPI ________________

EAC _____________________

4. Mary is the project manager for a web design project for Newberry Pet Foods. So far in the six weeks (of the twelve week project), Mary’s team has completed five tasks which had a combined planned value of $7800. However, the team spent $8200 to complete those tasks. She has five additional tasks to complete the project. What are the PV, EV, AC, CV, SV, CPI, and SPI for Mary’s project?

5 .Consider the following information:

PV=6500

EV=5000

AC=7200

BAC=32000

Expected Duration=12 weeks

Calculate the following:

CV __________________

SV __________________

CPI __________________

SPI __________________

EAC __________________

Duration at Completion _______________

Task

Predecessors

Duration in days

Planned Value ($)

Actual Cost ($)

Percent Complete

A

None

2

500

650

100

B

None

3

1000

1500

100

C

A

2

200

300

50

D

A

5

600

600

20

E

B ,C

6

1200

550

10

Explanation / Answer

1. Ans :
AC = 650+1500+300+600+550 = 3600
EV = (100+100+50+20+10)% * (AC)
EV = (280/100)*3600 = 1570.50
BAC = 32000
PV = 500+1000+200+600+1200 = 3500

CV = EV – AC = 1570.50 - 3600 = -2029.50

SV = EV – PV = 1570.50 - 3500 = -1929.50

CPI = EV / AC = 1570.50/3600 = 0.4362
SPI =   = 157.50/ 3500 = 0.4487

EAC = AC + (BAC – EV) = 3600 +32000 - 1570.50 = 34029.5

2. Ans :
PV = 6700
EV = 6100
AC = 7300
BAC = 38900
CPI = EV / AC = 6100/7300 = 0.8356
SPI = EV / PV = 6100/6700 = 0.9104
EAC = AC + (BAC – EV) = 7300 + 38900 - 6100 = 40100


3. Ans :
pv = 600+1000+200+1000+1200+10000+700+1600 = 16300
AC = 650+1500+300+600+1200+12000+0+0 = 16250
BAC = ((100+100+100+100+100+75)/100)*16250 = 93437.5
EV = (500/100)*16300 = 81500
CV = EV – AC = 81500 - 16250 = 65250

SV = EV – PV = 81500 - 16300 = 65200

CPI = EV / AC = 81500/ 16250 = 5.015
SPI = EV / PV = 81500/16300 = 5.00

EAC = AC + (BAC – EV) = 16250+93437.5 - 81500 = 28187.5


4. Ans :
PV = 7800
AC = 8200
EV = (50/100)*8200 = 4100
CV = EV - AC = 4100 - 8200 = -4100
SV = EV – PV = 4100 - 7800 = -3700
CPI = EV / AC = 4100/8200 = 0.5
SPI = EV / PV = 4100/ 7800 = 0.5256

5. Ans :

CV = EV – AC = 5000 - 7200 = -2200

SV = EV – PV = 5000 - 6500 = -1500

CPI = EV / AC = 5000/7200 = 0.6944
SPI = EV / PV = 5000/6500 = 0.7692

EAC = AC + (BAC – EV) = 7200 + (32000 - 5000) = 34200

Hire Me For All Your Tutoring Needs
Integrity-first tutoring: clear explanations, guidance, and feedback.
Drop an Email at
drjack9650@gmail.com
Chat Now And Get Quote