2:03 PM moodle.selu.edu oo AT&T; 9 of 11 9. For the network shown below with all
ID: 3588131 • Letter: 2
Question
2:03 PM moodle.selu.edu oo AT&T; 9 of 11 9. For the network shown below with all times indicating weeks, answer the following questions a) b) c) d) What is the impact on the end date of the project if activity B slips by two wecks? What is the impact on the end date of the project if activity E slips by one week? What is the impact on the end date of the project if activity D slips by two wecks? If the customer offered you bonus for completing the project in sixteen wecks or less, which activities would you focus on first as part of crashing (compression) analyses? START FINISHExplanation / Answer
a.No impact on schedule as B's output is required in 12th week
b. E slips by one week means project slips by a week
c.D slips by 2 weeks, no slippage in project. D gets finished by 15the
week where as E finishes by 18th week so D has 3 week margin.
d. If compression happens it has to happen on the critical path.So in this
case activities to be considered as A,C and E
Related Questions
Hire Me For All Your Tutoring Needs
Integrity-first tutoring: clear explanations, guidance, and feedback.
Drop an Email at
drjack9650@gmail.com
drjack9650@gmail.com
Navigate
Integrity-first tutoring: explanations and feedback only — we do not complete graded work. Learn more.