Academic Integrity: tutoring, explanations, and feedback — we don’t complete graded work or submit on a student’s behalf.

The percentage utilization for the sequence developed using the FCFS rule = % (e

ID: 359436 • Letter: T

Question

The percentage utilization for the sequence developed using the FCFS rule = %

(enter your response as a percentage rounded to two decimal places).

The average number of jobs in the system for the sequence developed using the FCFS rule =

jobs (round your response to two decimal places).

The average tardiness (job lateness) for the sequence developed using the FCFS rule =

nothing

days (round your response to two decimal places).

b) Using the EDD (earliest due date) decision rule for sequencing the jobs, the order is (to resolve a tie, use the order in which the jobs were received):

The total flow time for the sequence developed using the EDD rule =

nothing

days (round your response to two decimal places).

The percentage utilization for the sequence developed using the EDD rule =

nothing%

(enter your response as a percentage rounded to two decimal places).

The average number of jobs in the system for the sequence developed using the EDD rule =

nothing

jobs (round your response to two decimal places).

The average tardiness (job lateness) for the sequence developed using the EDD rule =

nothing

days (round your response to two decimal places).

c) Using the SPT (shortest processing time) decision rule for sequencing the jobs, the order is (to resolve atie, use the order in which the jobs were received):

The total flow time for the sequence developed using the SPT rule =

nothing

days (round your response to two decimal places).

The percentage utilization for the sequence developed using the SPT rule =

nothing%

(enter your response as a percentage rounded to two decimal places).

The average number of jobs in the system for the sequence developed using the SPT rule =

nothing

jobs (round your response to two decimal places).

The average tardiness (job lateness) for the sequence developed using the SPT rule =

nothing

days (round your response to two decimal places).

d) Using the LPT (longest processing time) decision rule for sequencing the jobs, the order is (to resolve atie, use the order in which the jobs were received):

The total flow time for the sequence developed using the LPT rule =

nothing

days (round your response to two decimal places).

The percentage utilization for the sequence developed using the LPT rule =

nothing%

(enter your response as a percentage rounded to two decimal places).

The average number of jobs in the system for the sequence developed using the LPT rule =

nothing

jobs (round your response to two decimal places).

Homework: Chapter 15: Short-Term Scheduling Score: 0.21 of 1 pt 3 of 5 (5 complete HW Score: 81.43%, 4.07 of 5 pts Problem 15.15 Question Help a) Using the FCFS first come, first served) decision rule for sequencing the jobs, the order is (assume that jobs came in the order inThe following jobs are waiting to be processed at the same machine center. Jobs are logged as they arrve which they are listed in the table) Duration (days) Due Date 313 312 325 314 315 Job 16 40 Al dates are specified as manufacturing planning calendar days Assume that all jobs arrive on day 275. Assume each jab starts at the baginning af tha day and finishes at the end of the day (a job that hegins on day 275 and takes8 days will finish an day 282, and the naxt job begins in the moming of day 203). Compute all times based on inibiating work on day 275 The average tardinass (job lateness) far the sequencn develapad using the FCFS rula-14 60 days fround your rosps to tvo dscimal places) le-| |% enter your response es e percentage rounded to The percentage utilization for the sequence developed using the FCFS iwo decimai placea). Enter your answer in the answer box and then click Check Answer 2 eamsining Clear All Check Answer

Explanation / Answer

FCFS

Job Sequence

Due Date

Duration (Days)

A

313

8

B

312

16

C

325

40

D

314

5

E

314

3

       

Job work time

flow time

Due Date

job lateness

8

8

39

0

16

24

38

0

40

64

51

13

5

69

40

29

3

72

40

32

sum

72

237

74

Due date

The jobs arrive on day 275

Hence due date = given due date – 274

Eg. For A, due date=313-274 =39 ,

we have 39 days to complete A

flow time-

cumulative sum of work time at each job level

eg 8+16=24

16+40=64 ....

job lateness- if the job’s flow time is less than or equal to due date then, lateness=0.

Otherwise, lateness= flow time -due date

The percentage utilization for the sequence developed using the FCFS rule = %

Utilization =     (Total job work time/Sum of total flow time)*100

                               = 72/237 = 30.38%

The average number of jobs in the system for the sequence developed using the FCFS rule =

Average number of jobs in the system = Sum of total flow time/Total job work time =237/72=3.29 JOBS

The average tardiness (job lateness) for the sequence developed using the FCFS rule =

Average tardiness (job lateness) = Total late days/ Number of jobs =74/5=14.80

b) Using the EDD (earliest due date) decision rule for sequencing the jobs, the order is (to resolve a tie, use the order in which the jobs were received):

       

Job Sequence

Due Date

B

312

A

313

D

314

E

314

C

325

Job work time

flow time

Due Date

job lateness

16

16

38

0

8

24

39

0

5

29

40

0

3

32

40

0

40

72

51

21

sum

72

173

21

The total flow time for the sequence developed using the EDD rule =173

The percentage utilization for the sequence developed using the EDD rule = ( 72/173 ) *100 = 41.62%

The average number of jobs in the system for the sequence developed using the EDD rule =173/72 =2.40

The average tardiness (job lateness) for the sequence developed using the EDD rule =21/5 = 4.2

c) Using the SPT (shortest processing time) decision rule for sequencing the jobs, the order is (to resolve a tie, use the order in which the jobs were received):

       

Job Sequence

Due Date

Duration (Days)

E

314

3

D

314

5

A

313

8

B

312

16

C

325

40

       

Job work time

flow time

Due Date

job lateness

3

3

40

0

5

8

40

0

8

16

39

0

16

32

38

0

40

72

51

21

sum

72

131

21

The total flow time for the sequence developed using the SPT rule = 131

The percentage utilization for the sequence developed using the SPT rule = (72/131)*100 =54.96

The average number of jobs in the system for the sequence developed using the SPT rule = 131/72=1.82

The average tardiness (job lateness) for the sequence developed using the SPT rule =21/5=4.2

d) Using the LPT (longest processing time) decision rule for sequencing the jobs, the order is (to resolve a tie, use the order in which the jobs were received):

Job Sequence

Due Date

Processing Time

C

325

40

B

312

16

A

313

8

D

314

5

E

314

3

Job work time

flow time

Due Date

job lateness

40

40

51

0

16

56

38

18

8

64

39

25

5

69

40

29

3

72

40

32

sum

72

301

104

The total flow time for the sequence developed using the LPT rule = 301

The percentage utilization for the sequence developed using the LPT rule = (72/301)*100 =23.92%

The average number of jobs in the system for the sequence developed using the LPT rule =301/72 =4.18

The average tardiness (job lateness) for the sequence developed using the LPT rule = 104/5 =20.8

Job Sequence

Due Date

Duration (Days)

A

313

8

B

312

16

C

325

40

D

314

5

E

314

3

Hire Me For All Your Tutoring Needs
Integrity-first tutoring: clear explanations, guidance, and feedback.
Drop an Email at
drjack9650@gmail.com
Chat Now And Get Quote