Assume that Product Z is made of two units of A and three units of B. Ais made o

ID: 361209 • Letter: A

Question

Assume that Product Z is made of two units of A and three units of B. Ais made of four units of C and four of D. Dis made of two units of E Lead times for purchase or fabrication of each unit to final assembly are: Z takes two weeks: A, B, C, and D take one week each; and E takes three weeks. Fifty six units of Product Z are required in Period 10. (Assume that there is currently no inventory on hand of any of these items.) b. Develop an MRP planning schedule showing gross and net requirements and order release and order receipt dates. (Leave no cells blank - be certain to enter "0" wherever required.) | 10 Item z OH - 0 LT-2 SS = 0 Q=L4L Period Gross requirements Scheduled receipts Projected available balance Net requirements Planned order receipts Planned order releases Item A OH = 0 LT=1 SS = 0 Q- L4L Gross requirements Scheduled receipts Projected available balance Net requirements Planned order receipts Planned order releases Item B OH - 0 LT-1 SS = 0 Q= L4L Gross requirements Scheduled receipts Projected available balance Net requirements Planned order receipts Planned order releases Item C OH = 0 LT=1 SS-0 Q-L4L Gross requirements Scheduled receipts Projected available balance Net requirements Planned order receipts Planned order releases Item D OH-0 LT-1 SS = 0 Q= L4L Gross requirements Scheduled receipts Projected available balance Net requirements Planned order receipts Planned order releases Item E OH = 0 LT=3 SS-0 Q- L4L Gross requirements Scheduled receipts Projected available balance Net requirements Planned order receipts Planned order releases

Explanation / Answer

The MRP table for all components are presented below. Blank spaces should be considered as “Zero”

Item: Z On hand =0, SS = 0

                                                              Week

Lot size: Lot for Lot

Lead time: 2 week

1

2

3

4

5

6

7

8

9

10

Gross Requirement

56

Scheduled receipt

0

Projected available balance

0

Net requirement

56

Planned order receipt

56

Planned order release

56

Item: A, On hand=0, SS = 0

                                                              Week

Lot size: Lot for Lot

Lead time: 1 weeks

1

2

3

4

5

6

7

8

9

10

Gross Requirement

112

Scheduled receipt

0

Projected available balance

0

Net requirement

112

Planned order receipt

112

Planned order release

112

Item: B , SS = 0 On hand=0

                                                              Week

Lot size: Lot for Lot

Lead time: 1 weeks

1

2

3

4

5

6

7

8

9

10

Gross Requirement

168

Scheduled receipt

0

Projected available balance

0

Net requirement

168

Planned order receipt

168

Planned order release

168

Item: C, SS = 0 , On hand = 0

                                                              Week

Lot size: L4L

Lead time: 1 week

1

2

3

4

5

6

7

8

9

10

Gross Requirement

448

Scheduled receipt

0

Projected available balance

0

Net requirement

448

Planned order receipt

448

Planned order release

448

Item: D, OH = , SS = 0

                                                              Week

Lot size:

Lot for Lot

Lead time: 1 weeks

1

2

3

4

5

6

7

8

9

10

Gross Requirement

448

Scheduled receipt

0

Projected available balance

0

Net requirement

448

Planned order receipt

448

Planned order release

448

Item: E

                                                              Week

Lot size: L4L

Lead time: 3 weeks

1

2

3

4

5

6

7

8

9

10

Gross Requirement

896

Scheduled receipt

0

Projected available balance

0

Net requirement

896

Planned order receipt

Planned order release

896

Item: Z On hand =0, SS = 0

                                                              Week

Lot size: Lot for Lot

Lead time: 2 week

1

2

3

4

5

6

7

8

9

10

Gross Requirement

56

Scheduled receipt

0

Projected available balance

0

Net requirement

56

Planned order receipt

56

Planned order release

56