Assume that Product Z is made of two units of A and three units of B. A is made
ID: 331895 • Letter: A
Question
Assume that Product Z is made of two units of A and three units of B. A is made of four units of C and four of D. D is made of two units of E.
Lead times for purchase or fabrication of each unit to final assembly are: Z takes two weeks; A, B, C, and D take one week each; and E takes three weeks.
Fifty six units OF Product Z are required in Period 10. (Assume that there is currently no inventory on hand of any of these items.)
Develop an MRP planning schedule showing gross and net requirements and order release and order receipt dates. (Leave no cells blank - be certain to enter "0" wherever required.)
Hint: enter "0" for "Scheduled receipts" and "Projected available balance"
Explanation / Answer
Solution :
Z, LT - 2, Lot - L4L On Hand 1 2 3 4 5 6 7 8 9 10 Total Gross Requirements 0 0 0 0 0 0 0 0 0 56 56 Scheduled Receipts 0 0 0 0 0 0 0 0 0 0 Projected On Hand 0 0 0 0 0 0 0 0 0 0 0 Net requirements 0 0 0 0 0 0 0 0 0 56 Planned order receipts 0 0 0 0 0 0 0 0 0 56 Planned order releases 0 0 0 0 0 0 0 56 0 0 A, LT - 1, Lot - L4L On Hand 1 2 3 4 5 6 7 8 9 10 Total Gross Requirements 0 0 0 0 0 0 0 112 0 0 112 Scheduled Receipts 0 0 0 0 0 0 0 0 0 0 Projected On Hand 0 0 0 0 0 0 0 0 0 0 0 Net requirements 0 0 0 0 0 0 0 112 0 0 Planned order receipts 0 0 0 0 0 0 0 112 0 0 Planned order releases 0 0 0 0 0 0 112 0 0 0 B, LT - 1, Lot - L4L On Hand 1 2 3 4 5 6 7 8 9 10 Total Gross Requirements 0 0 0 0 0 0 0 168 0 0 168 Scheduled Receipts 0 0 0 0 0 0 0 0 0 0 Projected On Hand 0 0 0 0 0 0 0 0 0 0 0 Net requirements 0 0 0 0 0 0 0 168 0 0 Planned order receipts 0 0 0 0 0 0 0 168 0 0 Planned order releases 0 0 0 0 0 0 168 0 0 0 C, LT - 1, Lot - L4L On Hand 1 2 3 4 5 6 7 8 9 10 Total Gross Requirements 0 0 0 0 0 0 448 0 0 0 448 Scheduled Receipts 0 0 0 0 0 0 0 0 0 0 Projected On Hand 0 0 0 0 0 0 0 0 0 0 0 Net requirements 0 0 0 0 0 0 448 0 0 0 Planned order receipts 0 0 0 0 0 0 448 0 0 0 Planned order releases 0 0 0 0 0 448 0 0 0 0 D, LT - 1, Lot - L4L On Hand 1 2 3 4 5 6 7 8 9 10 Total Gross Requirements 0 0 0 0 0 0 448 0 0 0 448 Scheduled Receipts 0 0 0 0 0 0 0 0 0 0 Projected On Hand 0 0 0 0 0 0 0 0 0 0 0 Net requirements 0 0 0 0 0 0 448 0 0 0 Planned order receipts 0 0 0 0 0 0 448 0 0 0 Planned order releases 0 0 0 0 0 448 0 0 0 0 E, LT - 3, Lot - L4L On Hand 1 2 3 4 5 6 7 8 9 10 Total Gross Requirements 0 0 0 0 0 896 0 0 0 0 896 Scheduled Receipts 0 0 0 0 0 0 0 0 0 0 Projected On Hand 0 0 0 0 0 0 0 0 0 0 0 Net requirements 0 0 0 0 0 896 0 0 0 0 Planned order receipts 0 0 0 0 0 896 0 0 0 0 Planned order releases 0 0 896 0 0 0 0 0 0 0Related Questions
drjack9650@gmail.com
Navigate
Integrity-first tutoring: explanations and feedback only — we do not complete graded work. Learn more.