Assume that Product Z is made of two units of A and four units of B. A is made o

ID: 368138 • Letter: A

Question

Assume that Product Z is made of two units of A and four units of B. A is made of three units of C and four of D. D is made of two units of E.

     Lead times for purchase or fabrication of each unit to final assembly are: Z takes two weeks; A, B, C, and D take one week each; and E takes three weeks.

     Sixty nine units OF Product Z are required in Period 10. (Assume that there is currently no inventory on hand of any of these items.)

Develop an MRP planning schedule showing gross and net requirements and order release and order receipt dates. (Leave no cells blank - be certain to enter "0" wherever required.)

Assume that Product Z is made of two units of A and four units of B. A is made of three units of C and four of D. D is made of two units of E.

     Lead times for purchase or fabrication of each unit to final assembly are: Z takes two weeks; A, B, C, and D take one week each; and E takes three weeks.

     Sixty nine units OF Product Z are required in Period 10. (Assume that there is currently no inventory on hand of any of these items.)

Explanation / Answer

Material resource planning:

Product Time taken 1 2 3 4 5 6 7 8 Z 2 WEEKS Start A 1 WEEK Start Due B 1 WEEK Start Due C 1 WEEK Start Due D 1 WEEK Start Due E 3 WEEKS Start Due