A manufacturer is contemplating a switch from buying to producing a certain item
ID: 361642 • Letter: A
Question
A manufacturer is contemplating a switch from buying to producing a certain item. Setup cost would be the same as ordering cost. The production rate would be about double the usage rate. (Can you please show me how you did it)
1) Compared to the EOQ, the economic run size would be
A) the same
B) approx 20% larger
C) approx 40% larger
D) 20% smaller
E) approx 40% smaller
2. Compared to the EOQ, the miximum inventory would be
A) approx 70% higher
B) approx 30% higher
C) the same
D) approx 30% lower
E) approx 70% lower
Explanation / Answer
EOQ = (2*Co*D/Cc)
EPQ= (2*Co*D/(Cc*(1-x)))
x=D/P
D = demand rate
P =production rate
Co=ordering cost
Cc=holding cost
1) The production rate would be about double the usage rate.
hence, P = 2D
x=D/2D=0.5
EPQ= (2*Co*D/((1-0.5)*Cc))
EPQ= (2*Co*D/0.5Cc)
EPQ= (1/0.5)*EOQ
EPQ= (2)*EOQ
EPQ=1.41*EOQ
Hence, EPQ is around 40% larger than EOQ.
Ans.: c) EPQ will be approximately 40% larger than the EOQ.
2) Compared to the EOQ, the maximum inventory would be
maximum inventory = Q
EPQ = 1.41 EOQ
EPQ = 1.41*Q
Q=EPQ/1.41
Q=0.71 EPQ
Hence, compared to EOQ, maximum inventory in EPQ is only 70% of that in EOQ model.
Ans.: D) compared to the EOQ, the maximum inventory would be approx 30% lower.
EOQ = (2*Co*D/Cc)
EPQ= (2*Co*D/(Cc*(1-x)))
x=D/P
D = demand rate
P =production rate
Co=ordering cost
Cc=holding cost
1) The production rate would be about double the usage rate.
hence, P = 2D
x=D/2D=0.5
EPQ= (2*Co*D/((1-0.5)*Cc))
EPQ= (2*Co*D/0.5Cc)
EPQ= (1/0.5)*EOQ
EPQ= (2)*EOQ
EPQ=1.41*EOQ
Hence, EPQ is around 40% larger than EOQ.
Ans.: c) EPQ will be approximately 40% larger than the EOQ.
2) Compared to the EOQ, the maximum inventory would be
maximum inventory = Q
EPQ = 1.41 EOQ
EPQ = 1.41*Q
Q=EPQ/1.41
Q=0.71 EPQ
Hence, compared to EOQ, maximum inventory in EPQ is only 70% of that in EOQ model.
Ans.: D) compared to the EOQ, the maximum inventory would be approx 30% lower.