Academic Integrity: tutoring, explanations, and feedback — we don’t complete graded work or submit on a student’s behalf.

The critical activities are What is the EF for Activity C? What is the LF for Ac

ID: 362169 • Letter: T

Question

The critical activities are What is the EF for Activity C? What is the LF for Activity E? What is the slack for the start of Activity C? What is the slack for the start of Activity E? What is the slack for the end of Activity E? What is the length of the project? time periods. From the following information, compute the early, late, and slack times for each activity. Identify the critical activities Additional Lag Relationships ID Duration Predecessor Lag Task Design Order Parts A. Start-start A to B C Code Software Assemble Debug Finish-start B to D3 Start-start C to E Finish-finish C to E2 Install E,D Lag 2 Lag 2 Lag 3 Lag 4

Explanation / Answer

All activities are critical i.e. A, B, C, D, E, F

What is the EF for Activity C? 11

What is the LF for Activity E? 13

What is the slack for the start of Activity C? 0

What is the slack for the start of Activity E? 3

What is the slack for the end of Activity E? 0

What is the length of the project? time periods. 14

Activity Duration ES EF LS LF Slack A 5 0 5 0 5 0 B 1 4 5 4 5 0 C 6 5 11 5 11 0 D 5 8 13 8 13 0 E 3 7 13 10 13 0 F 1 13 14 13 14 0
Hire Me For All Your Tutoring Needs
Integrity-first tutoring: clear explanations, guidance, and feedback.
Drop an Email at
drjack9650@gmail.com
Chat Now And Get Quote