Question l: Project Performance Measure: (Earned Value) (6 points) Given the pro
ID: 363396 • Letter: Q
Question
Question l: Project Performance Measure: (Earned Value) (6 points) Given the project network and baseline information below, complete the Table 3 & Table 4 Ouestion (la): Project status (SV, CV, CPI, SPI) at the end of period 4 and the end of period 8. (5 pts) Table 1. Network LEGEND ES ID EF SL LF SL 8 D 12 LS 8 4 12 12 F 15 0 12 3 15 7 E 10 9 3 12 Table 2. Planned value Project baseline (PV) in $) Task DUR ES 1 2 3 4 5 67 8 10 12 13 14 0 400 200 200 B 628 2400 200 600 200 600 200 600 C 5 29 21500 200 400 500 100 300 400 40 400 400 300 | 400 | 200 F 3 15 600 200 100 300 700 | 700 | 500 000 | 800 | 600 | 400 | 400 | 200 | 100 | 300 7100 7400 Period PW total 200 200 400 Cumulative PV total 200 | 400 800 1800 3700 4600Explanation / Answer
Table 3 Expected PV-AC PV-EV PV/AC PV/EV Task Ac % EV AC PV CV SV CPI SPI A 100% 400 300 400 100 0 1.333333 1 B 50% 1000 1000 800 -200 -200 0.8 0.8 C 33% 0 500 600 100 600 1.2 0 D 0% 0 0 0 0 0 0 0 E 0% 0 0 0 0 0 0 0 Cumm Total 1400 1800 1800 0 400 1 1.285714 Table 4 Expected PV-AC PV-EV PV/AC PV/EV Task Ac % EV AC PV CV SV CPI SPI A 100% 400 300 400 100 0 1.333333 1 B 100% 2400 2200 2400 200 0 1.090909 1 C 100% 400 1500 400 -1100 0 0.266667 1 D 25% 0 300 0 -300 0 0 0 E 33% 300 300 300 0 0 1 1 F 0% 0 0 0 0 0 0 0 Cumm Total 3500 4600 3500 -1100 0 0.76087 1
Related Questions
drjack9650@gmail.com
Navigate
Integrity-first tutoring: explanations and feedback only — we do not complete graded work. Learn more.