port from two auto plants to three dealerships Figure 1. Auto trans Question 3.
ID: 364230 • Letter: P
Question
port from two auto plants to three dealerships Figure 1. Auto trans Question 3. LP problem formulation-Bus Scheduling A bus company is planning to introduce a bus service to one City. The buses will operate on a 24-hour schedule starting at 00:00 and ending at 24:00. It has been decided also that each shift can start at every below: four-hour time intervals (e.g. 00:00, 4:00, 8:00 etc.). The demand for buses are is depicted in Table 2 Table 2. Bus demand per four-hour time period Time interval Bus demand 00:00-4:0 4:00-8:00 8:00- 12:00 12:00 16:00 16:00-20:00 20:00-24:00 4 8 10 7 12 4 Each shift is required to work 8-hours, based on the starting times above (e.g. a bus can start at 4:00 and end at 12:00, a bus can start at 8:00 and end at 16:00). The company wants to minimize the number of buses to operate under these rules on a daily basis t up the problem as an LP. Define variables, objective function and constraints.Explanation / Answer
Variables :
x1 - Number of buses starting at 00:00 hrs
x2 - Number of buses starting at 04:00 hrs
x3 - Number of buses starting at 08:00 hrs
x4 - Number of buses starting at 12:00 hrs
x5 - Number of buses starting at 16:00 hrs
x6 - Number of buses starting at 20:00 hrs
Constraints - Based on demand
x1 + x6 >= 4
x1 + x2 >=8
x2 + x3 >= 10
x3 + x4 >= 7
x4 + x5 >= 12
x5 + x6 >= 4
Objective - To minimise the number of buses
Minimise x1 + x2 + x3 + x4 + x5 + x6
Related Questions
Navigate
Integrity-first tutoring: explanations and feedback only — we do not complete graded work. Learn more.