Does this information (WBS) allow you to define any milestones of the project? W
ID: 3665181 • Letter: D
Question
Does this information (WBS) allow you to define any milestones of the project? Why or why not? What are they?
Mode Task Name 1 Conveyor Belt Project 1 day? Tue 16/2/2 Tue 16/2/2 Tue 16/2/2 Tue 16/2/2 Tue 16/2/2 Tue 16/2/2 Tue 16/2/2 Tue 16/2/2 Tue 16/2/2 Tue 16/2/2 Tue 16/2/2 Tue 16/2/2 Tue 16/2/2 Tue 16/2/2 Tue 16/2/2 Tue 16/2/2 Tue 16/2/2 Tue 16/2/2 1.1 Hardware 1 day? 1.1.1 Hardware specififcations 1.1.2 Hardware design 1.1.3 Hardware documentation 1.1.4 Prototypes 1.1.5 Prder circuit boards 1.1.6 Assemble preproduction models 1 day? 1 day? 1 day? 1 day? 1 day? 1 day? 4 1.2 Operatingi system Tue 16/2/2 Tue 16/2/2 Tue 16/2/2 Tue 16/2/2 Tue 16/2/2 Tue 16/2/2 Tue 16/2/2 Tue 16/2/2 Tue 16/2/2 Tue 16/2/2 Tue 16/2/2 Tue 16/2/2 Tue 16/2/2 Tue 16/2/2 Tue 16/2/2 Tue 16/2/2 Tue 16/2/2 Tue 16/2/2 Tue 16/2/2 Tue 16/2/2 Tue 16/2/2 Tue 16/2/2 Tue 16/2/2 Tue 16/2/2 Tue 16/2/2 Tue 16/2/2 Tue 16/2/2 Tue 16/2/2 Kernel specifications 1 day? 1 day? 1 day? 1 day? 1 day? 1 day? 1 day? 1.2.1 1.2.2 Drivers 12 1.2.2.1 Disk drivers 1.2.2.2 Serial 1/0 drivers 1.2.3 Memory management 1.2.4 Operatingi system documentation 1.2.5 Network interface 15 16 17 1.3 Utilities 1.3.1 Utilities specifications 1.3.2 Routine utilities 1.3.3 Complex utilities 1.3.4 Utilities documentation 1.3.5 Shell 1 day? 1 day? 1 day? 21 4 1.4 System integration 1.4.1 Architectural decisions 1.4.2 Integration first phase 1.4.3 System hard/software test 1.4.4 Project documentation Tue 16/2/2 Tue 16/2/2 Tue 16/2/2 Tue 16/2/2 Tue 16/2/2 Tue 16/2/2 Tue 16/2/2 Tue 16/2/2 1 day? 25 1 day?Explanation / Answer
This WBS does not permit you to characterize any points of reference of the venture since time is not yet characterized for the task deliverables. A breakthrough is a sufficiently great occasion in an undertaking or a critical control point in the venture that is effectively identification.The details you mentioned only software,hardware,system integration, requird more detials about project .
,Related Questions
Hire Me For All Your Tutoring Needs
Integrity-first tutoring: clear explanations, guidance, and feedback.
Drop an Email at
drjack9650@gmail.com
drjack9650@gmail.com
Navigate
Integrity-first tutoring: explanations and feedback only — we do not complete graded work. Learn more.