Academic Integrity: tutoring, explanations, and feedback — we don’t complete graded work or submit on a student’s behalf.

Homework: HW12 Score: 2.5 of 10 pts | 7 of 8 (8 complete) HW Score: 62.5%, 62.5

ID: 368158 • Letter: H

Question

Homework: HW12 Score: 2.5 of 10 pts | 7 of 8 (8 complete) HW Score: 62.5%, 62.5 of 100 Problem 3.11 b Question Help The following is a table of activities associated with a project at Rafay Ishfaq's software firm in Chicago, their durations and what activities each must precede B, C F (end) This exercise contains only parts b, c, and d b) The activities on the critical path are A-C-F c) The total project completion time for Rafay Ishfaq's software firm is 12 weeks. (Enter your response as a whole number) d) Determine the slack time for each of the activities. (Enter your responses as whole numbers.)

Explanation / Answer

Therefore slack is present for activities B and E

Activity Time Precedes Early Start Early Finish Late Start Late Finish Slack A 2 B,C 0 2 0 2 0 B 3 E 2 5 3 6 1 C 7 F 2 9 2 9 0 E 3 F 5 8 6 9 1 F 3 - 9 12 9 12 0