Q: Complete the following \"Reason column\" for your software engineering risk a
ID: 3692016 • Letter: Q
Question
Q: Complete the following "Reason column" for your software engineering risk analysis project.
Please Note that there is a sample for filling the reason column please see it.
Risk
Probability
Effects
Reason
Organizational financial problems force reductions in the project budget (7).
Low
Catastrophic
It is impossible to recruit staff with the skills required for the project (3).
High
Catastrophic
Key staff are ill at critical times in the project (4).
Moderate
Serious
Faults in reusable software components have to be repaired before these components are reused. (2).
Moderate
Serious
Changes to requirements that require major design rework are proposed (10).
Moderate
Serious
The organization is restructured so that different management are responsible for the project (6).
High
Serious
The database used in the system cannot process as many transactions per second as expected (1).
Moderate
Serious
The time required to develop the software is underestimated (12).
High
Serious
Software tools cannot be integrated (9).
High
Tolerable
Customers fail to understand the impact of requirements changes (11).
Moderate
Tolerable
Required training for staff is not available (5).
Moderate
Tolerable
The rate of defect repair is underestimated (13).
Moderate
Tolerable
The size of the software is underestimated (14).
High
Tolerable
Code generated by code generation tools is inefficient (8).
Moderate
Insignificant
A sample for Completing the reason column :-
Risk
Probability
Effects
Reason
Development of the wrong user interface which will result in redesign and implementation from scratch.(1)
High
Catastrophic
Probability of such risk is high due to the presence of more than one service and different requirements. It causes a catastrophic effect because it basically doesn’t meet the assigned requirements.
Depending on a technology that is still being developed. (2)
Low
Serious
The occurrence of this risk due to the presence of only one technology but it doesn’t usually happen and it causes a serious issue in the time and cost of the project.
Too much conflicts among team members developing the software will result in poor communication and therefore poor designing, incomplete work and late delivery of the product.(3)
Moderate
Catastrophic
Too much disagreement in any team designing has a chance of 50% occurring due to each member having a different point of view. If such risk occurs, it is going to cause a huge mess and an imbalance. Therefore, the project will not be delivered correctly and on time.
Replacement of team members or change in tasks among between the team members. (4)
High
Serious
Sometimes a member or more in a team can fail to complete his task and therefore pass it to another team member or probably switch tasks due to improper division of work. Also, team members might leave and therefore replaced by others which will cause conflicts related with time and organization.
Failing to integrate the software tools. (5)
High
Tolerable
In most cases, incorporating software tools along with the project is a concern. However, it is not that much of a concern because it can be easily fixed by training or by seeking the help of a specialist.
Introduction of new requirements according to the customer’s desire.(6)
Very High
Serious
Customers have unlimited requirements and expectations. This is why the risk of introducing new requirements is really high. In addition, it will cause re-developing or re-designing some software functions of the system and this is costly and time-consuming.
Software productivity rate is overestimated.(7)
High
Tolerable
Software productivity is often assumed to be quick by most developers. Nevertheless, they get surprised that it is not. However, it does not cause that much of a great impact on the development.
The size of the software and integration effort is underestimated. (8)
High
Serious
Misinterpretation of the amount of effort to build the software is always an issue. Developers don’t realise this issue until they start actually developing the functions of the system which is approximately halfway through the development process. They also don’t realise how bad it can get when time starts running out and the project is not even past halfway the assigned time for the project.
Risk
Probability
Effects
Reason
Organizational financial problems force reductions in the project budget (7).
Low
Catastrophic
It is impossible to recruit staff with the skills required for the project (3).
High
Catastrophic
Key staff are ill at critical times in the project (4).
Moderate
Serious
Faults in reusable software components have to be repaired before these components are reused. (2).
Moderate
Serious
Changes to requirements that require major design rework are proposed (10).
Moderate
Serious
The organization is restructured so that different management are responsible for the project (6).
High
Serious
The database used in the system cannot process as many transactions per second as expected (1).
Moderate
Serious
The time required to develop the software is underestimated (12).
High
Serious
Software tools cannot be integrated (9).
High
Tolerable
Customers fail to understand the impact of requirements changes (11).
Moderate
Tolerable
Required training for staff is not available (5).
Moderate
Tolerable
The rate of defect repair is underestimated (13).
Moderate
Tolerable
The size of the software is underestimated (14).
High
Tolerable
Code generated by code generation tools is inefficient (8).
Moderate
Insignificant
Explanation / Answer
7.If the project budjet is low,then the effect is catastropic because organisation earn their bread by completing projects.So to earn good income for the organisation,project budget should be high.
3.For meeting deadlines,in the project,very good skills are required in the staffs to face new challenges coming in the project.If they are not able too recruit such kind of staff,then the effect will be catastropic because,the deadline will not be met,loss of huge income,and chances of permanently losing client or customer.
4.key staffs should be present at critical times in the project,to haandle unexpected situation.If they are not there,then the effect will be serious because whle project will go into the messy situation and others will not know how to handle.
2.Faults in reusable components have to be fixed before they are reused because,these faults will create a furthur issue and because of these faults,new faults will appear,causing unexpected problems which is a very serious issue.These faults can also lead to failure.
10.Changes to requirements that require major design rework are proposed because the design after making changes may be very efficient.These changes must not be ignored.These changes will help us to do our work in very easy way.It may save lot of cost which has to be put into the project.
6.The organization should restructured so that different management are responsible for the project ,this is very efficient ,because,dividing people in which they are better earn more profit.
1.The database used in the system cannot process as many transactions per second as expected .This may happen due to the overload and corruption of data .This is a serious issue because,we cannot work in the speed in which we expect.This will cause loss of time.
12.Underestimating he time required to develop the software is an serious issue because unexpected problems are common in softwares and this may delay deadlines .
5.As required training for staff is not available ,this causes more time to staffs to get adjusted to new platform and it delays the completion of project.