Put yourself in the shoes of a project manager. You must create and present a pr

ID: 370319 • Letter: P

Question

Put yourself in the shoes of a project manager. You must create and present a project proposal for a home renovation that has value and persuade your management (which is your instructor) that it is worthy of being part of the project portfolio. The objective of the project is to include information from the table below

Deliverable

Audience

Objective of Deliverable

Approx. length

What to include

Comments

Project Report

Sponsor, stakeholders, project team, future project teams.

Self-contained description of entire project, including problem approached, solution, final deliverables, success metrics, conclusions, and lessons learned. This is the project artifact that will be available in the future about the

project.

5-20 pages

Cover page and detailed table of contents

PROJECT OBJECTIVE & SCOPE

ORGANIZATION AND PROJECT CRITICAL SUCCESS FACTORS

ASSUMPTIONS

PROJECT ORGANIZATION

Work Breakdown Structure

Responsibility Chart

Schedule

Resource Allocation

FINANCIAL PLAN

MONITORING AND CONTROL PLAN

RISK ASSESSMENT

SUMMARY

References and Appendices

: Relevant project management documentation, including an example of team meeting notes.

See sample:

Presentation

Sponsor, stakeholders, project team, peers

Highlight purpose of project, solution, and major accomplishments. Highlight unique aspects of project, including lessons learned.

Depends on duration

Project Objective

Overview: product deliverable

Approach & Plan: major interim deliverables, risk analysis, etc - focus on unique/interesting aspects

Results: product deliverable and measures of success. Include pictures when possible.

Lessons Learned

Focus on the unique elements of your project - what will your audience find most relevant and interesting?y

Deliverable

Audience

Objective of Deliverable

Approx. length

What to include

Comments

Project Report

Sponsor, stakeholders, project team, future project teams.

Self-contained description of entire project, including problem approached, solution, final deliverables, success metrics, conclusions, and lessons learned. This is the project artifact that will be available in the future about the

project.

5-20 pages

Cover page and detailed table of contents

PROJECT OBJECTIVE & SCOPE

ORGANIZATION AND PROJECT CRITICAL SUCCESS FACTORS

ASSUMPTIONS

PROJECT ORGANIZATION

IMPLEMENTATION PLAN

Work Breakdown Structure

Responsibility Chart

Schedule

Resource Allocation

FINANCIAL PLAN

MONITORING AND CONTROL PLAN

RISK ASSESSMENT

SUMMARY

References and Appendices

: Relevant project management documentation, including an example of team meeting notes.

See sample:

Presentation

Sponsor, stakeholders, project team, peers

Highlight purpose of project, solution, and major accomplishments. Highlight unique aspects of project, including lessons learned.

Depends on duration

Project Objective

Overview: product deliverable

Approach & Plan: major interim deliverables, risk analysis, etc - focus on unique/interesting aspects

Results: product deliverable and measures of success. Include pictures when possible.

Lessons Learned

Focus on the unique elements of your project - what will your audience find most relevant and interesting?y

Explanation / Answer

--

Table of Contents for the project:

Table of Contents

Table of Contents. 1

Cover Page: 2

Objective of the Project: 3

Scope of the Project: 3

Organization of the project: 4

Critical Success factors for the project: 6

Assumptions made: 6

How the project is organized: 7

Plan to implement: 8

Responsibility Chart (Hierarchy, who does what work) 9

Time schedule: 10

Resources Allocation: 11

Financial Planning: 12

Risk Assessment: 14

Summary: 15

Citation and References: 16

Cover Page:

Construction and home renovation

Objective of the Project:

Scope of the Project:

Organization of the project:

Budget for the following:

Critical Success factors for the project:

(The success of the Project depends on these major pillars of the project)

Assumptions made:

How the project is organized:

Plan to implement:

Work Break Down Structure (WBS)

Responsibility Chart (Hierarchy, who does what work)

Time schedule:

Resources Allocation:

Civil Engineers

Funds

Masons

Bricks

Sand

Cement

Steel rods

and other construction materials

Financial Planning:

Monitoring and control of the financial plan:

So we are borrowing 10 million, put in the work for 2 years and repay 11 million

When the sale price of 50 homes is 10 million, the construction cost can be aligned in such a way that there is a 30% return on Investment (ROI)

m = million

100 - 130

10 million - 130 * 10 million / 100 = 13 million

So we build houses for 10 million and sell them for 13 million

Repay the interest of 1 million and retain a profit of $12 million - not bad for a 2 year project work

so, for the $10 m, we can build 65 houses, sellable at 65 * 200,000 = $13, 000, 000   = $13 million

So these extra constructions of 15 houses are the ROI or profit

Risk Assessment:

Summary:

Over al, the project looks good, borrow $10 m, reap $13 m in just few years may look attractive as long as the market for housing and he supply demand goes in order

Citation and References:

Small business advice panel, Oxford University Press;

Project Plan to renovate 50 homes and resell (make bulk and save)

6 month per home; but 2 years for building 50 homes at a stretch

Median Home Sales price in USA

$200,000

50 homes

50*200,000= $10 million =

$10,000,000.00

Home Loan interest rate = 4%

Business loan interest rate = 9%

Equated Monthly Installements (EMI)

$456,847

Total Interest to be repaid

$964,338

Total Payment (Principal & Interest)

$10.9 million approx = $11 million

$10,964,338.00

So we are borrowing 10 million, put in the work for 2 years and repay 11 million

Project Plan to renovate 50 homes and resell (make bulk and save)

6 month per home; but 2 years for building 50 homes at a stretch

Median Home Sales price in USA

$200,000

50 homes

50*200,000= $10 million =

$10,000,000.00

Home Loan interest rate = 4%

Business loan interest rate = 9%

Equated Monthly Installements (EMI)

$456,847

Total Interest to be repaid

$964,338

Total Payment (Principal & Interest)

$10.9 million approx = $11 million

$10,964,338.00

So we are borrowing 10 million, put in the work for 2 years and repay 11 million