A project has only four activities: A, B, C, and D. The duration of these activi

ID: 370697 • Letter: A

Question

A project has only four activities: A, B, C, and D.

The duration of these activities are: 32, 35, 49, and 85 days, respectively.

Activity A and B have no immediate predecessor. They can start as soon as the project starts.

Activity D has activity A and B as its immediate predecessors. Activity A is the immediate predecessor of activity C.

No work will be done on weekends and federal holidays.

If the project starts at the beginning of June 21, 2017, when will activity D start and finish (actual dates)?

You must show brief calculation and explanation.

30.###########################

Federal Holidays 1. Monday, January 2, 2017 2. Monday, January 16, 2017 3. Monday, February 20, 2017 4. Monday, May 29, 2017 5. Tuesday, July 4, 2017 6. Monday, September 4, 2017 7. Monday, October 9, 2017 8. Friday, November 10, 2017 9. Thursday, November 23, 2017 10. Monday, December 25, 2017 11. Monday, January 1, 2018 12. Monday, January 15, 2018 13. Monday, February 19, 2018 14. Monday, May 28, 2018 15. Wednesday, July 4, 2018 16. Monday, September 3, 2018 17. Monday, October 8, 2018 18. Monday, November 12, 2018 19. Thursday, November 22, 2018 20. Tuesday, December 25, 2018 21. Tuesday, January 1, 2019 22. Monday, January 21, 2019 23. Monday, February 18, 2019 24. Monday, May 27, 2019 25. Thursday, July 4, 2019 26. Monday, September 2, 2019 27. Monday, October 14, 2019 28. Monday, November 11, 2019 29. Thursday, November 28, 2019

30.###########################

Explanation / Answer

Project starts on June 21, 2017. The first activity is A.

Given: Activity A and B have no immediate predecessor. They can start as soon as the project starts. Let us begin them as independent parallel activities.

Activity D has activity A and B as its immediate predecessors. Activity A is the immediate predecessor of activity C.

A takes 32 days. Between 21st July and 23rd August, no. of Federal Holidays = 0; No. of weekends = 4 = 8 days. So effectively, A will be completed by 31st August 2017 (23+8).

Activity B also starts from 21st July. B will take 35 days. So scheduled completion for B is by 3rd September 2017 (Applying same reasoning as for A)

C begins on 1st September, just after A is completed. Since D has A and B as its immediate predecessors, it cannot start before 3rd September. So D begins from 5th September (Since 4th sept is a federal holiday).