Compute the early, late, and the slack times for the activities in the network b
ID: 371760 • Letter: C
Question
Compute the early, late, and the slack times for the activities in the network below
Assume only 3 people is available to comple the project.
1) In this time constrained network which activities are critical(no slack)?
2)What is the time constrained project duration?
Legend ES ID EF LS Resource Scheduled resource load chart with ES and slack updates D RES DUR ES LF SL0 1 2 3 45 67 89 10 11 12 13 14 15 3 1 5 06 1 4 1 6 10 0 5 24 5 10 1 6 2 3 10 13 0 Resources scheduled Resources avalable 3 3 33 33 3 3 3 3 3 33 33Explanation / Answer
Minimum slack is 1.
minimum path is ID 2 ,5 ,6.
slack for activity 1= 1 , 4 = 0 , 5 =1.
critical activities are 2, 4 ,6
Related Questions
Hire Me For All Your Tutoring Needs
Integrity-first tutoring: clear explanations, guidance, and feedback.
Drop an Email at
drjack9650@gmail.com
drjack9650@gmail.com
Navigate
Integrity-first tutoring: explanations and feedback only — we do not complete graded work. Learn more.