15. You have an activity where the early start is week 6, the early finish is we
ID: 372297 • Letter: 1
Question
15. You have an activity where the early start is week 6, the early finish is week 10, the latest start is week 14, and the latest finish is week 18. Determine the slack in this activity. a. 4 weeks b. 6 weeks c. 8 weeks d. 10 weeks e. none of the above 16. What is the difference between PDM and ADM in project management? a. PDM places activities on nodes while ADM places activities on arrows b. ADM is also known as AOA, while PDM is sometimes referred to as GERT c. ADM hosts activities on nodes while PDM hosts activities on arrows d. PDM can have 2 types of relationships between tasks; ADM can have I type of relationship between tasks e. None of the above 17. As a new project manager who has never managed a project before, you've been asked to plan a new project during planning in order to improve your chance of success? It would be best in this situation to rely on a. your intustion b. historical information c. stakeholder analysis d. configuration management e all of the above 18. You are in the planning stage of a project. Walking down the hallway, your supervisor mumbles, Don't forget job shadowing. Job shadowing is a technique used in: defining the project scope collecting product requirements creating the WBS developing the stakeholder management strategy none of the above a. b. c. d. e. 19. Depending on the nature of the project, you might have many people approving your project management plan. What is the one signature you should be sure to get? The a. PMO director · Leader of the core team c. Sponsor d. Project champion e. None of the above 20. Which of the following is not true? Probability is expressed as a number between 0 and 1 b. a. Probability of zero means the certainty that an event will definitely not occur e. Probability is expressed from-1 to + d. e Probability of I means the certainty that an event will definitely occur Probability is expressed as a number between 0% to 100% 21. At the beginning of an iteration, the team will work to determine how many of the highest priority items on the backlog list can be delivered within the next iteration. At the end of each iteration, the product should be ready for review by the: a. project manager b. functional manager c. executive management d. customer e project championExplanation / Answer
15) Slack = LF - EF = LS - ES
LF = 18
EF = 10
Slack = 18-10 = 8
Ans C
16) A
In ADM (Arrow diagramming method), the activities are placed on Arrows whereas in PDM, the activities are on Nodes
17) D
Configuration management is the engineering process to maintain product performance along with operational and design requirement
18) E
Job shadowing is the technique to learn about particular job by getting involved in day to day activity
Related Questions
Hire Me For All Your Tutoring Needs
Integrity-first tutoring: clear explanations, guidance, and feedback.
Drop an Email at
drjack9650@gmail.com
drjack9650@gmail.com
Navigate
Integrity-first tutoring: explanations and feedback only — we do not complete graded work. Learn more.