37. One of the following is not normally listed as one of the most important responsibilities of a project manager a. planning b. integrating plans c. executing plans d. closing plans e. monitoring plans 38. Which of the following is not a major component of the project planning phase? a. Objective b. Schedule c. Regulation d. Budget e. All of the above 39. At the working group or functional level, planning must include the following, except a. agreement on purpose b. assignment and acceptance of group responsibilities c. coordination of work activities d. lateral communication e. all of the above 40. A network-based technique that allows for branching and looing is: a. PERT b. GERT c. PDM d. ADM e. AON 41. The most common constraint or relationship in a precedence network is: a. Start-to-start b. Start-to-finish c. Finish-to-start d. Finish-to-finish e. None of the above 42. Increasing customer participation in the service process: a. can build inventories in slack periods in manufacturing b. involves using part-timers during holiday seasons c. results in a chase demand strategy d. increases capacity and stretches physical resources 43. Which of the following is considered to be a bottom-up estimate rather than a top-down estimate? a. Engincering estimates b. Parametric estimates c. Analogy estimates d. Systematic estimates e. None of the above 45. Which of the following factors refer to conditions, not under the control of the project team, that influence constraint, or direct the project? a. Organizational process assets b. Work performance information c. Enterprise environmental factors d. Project management plan updates e. Any of the aboveExplanation / Answer
37. Answer- D. Closing plans. A project manager’s hey responsibilities include planning a monitoring the project, managing project risks and resources etc. but not closing plans.
38. Answer- E. All of the above. The Five major Components of project planning are scope (the objective of the project), schedule (which highlights the deliverables), Regulation (authority is given to a manager to take decisions) and budget (determines the costs involved to complete the project).
39. Answer- E. All of the above. Functional level planning includes planning the resources which can help best in completing the projects, career planning and development.
40. Answer- B. GERT. GERT stands for Graphical Evaluation and Review Technique that allows probabilistic treatment of both network logic and estimation of activity duration.