please note: All the answers are taken from the given MRP schedule: 24. Period 2

ID: 373733 • Letter: P

Question

please note: All the answers are taken from the given MRP schedule:

24. Period 2,3,4,5,6 and 7 have planned gross requirements for Z.

25. Periods 2, 4 and 6 have planned order release for Z.

26. Projected on-hand at the beginning of period 1 for Z = 400. (the MRP shows 400 as projected on hand (beginning) in period 0, but the data above shows on-hand as 800. This value in the answer has been taken from the MRP given)

27. What is the projected on-hand at the end of period 8 for Z =700

28. Planned order release for Z for period 1 = 0

29. Planned order release for Z for period 2 = 1500

30. Planned order release for Z for period 3 =0

31. Planned order release for Z for period 4 = 1500

32. Planned order release for Z for period 5 = 0

33. Planned order release for Z for period 6 = 1500

34. Planned order release for Z for period 7=0

35. Planned order release for Z for period 8=0

24. Period 2,3,4,5,6 and 7 have planned gross requirements for Z.

25. Periods 2, 4 and 6 have planned order release for Z.

26. Projected on-hand at the beginning of period 1 for Z = 400. (the MRP shows 400 as projected on hand (beginning) in period 0, but the data above shows on-hand as 800. This value in the answer has been taken from the MRP given)

27. What is the projected on-hand at the end of period 8 for Z =700

28. Planned order release for Z for period 1 = 0

29. Planned order release for Z for period 2 = 1500

30. Planned order release for Z for period 3 =0

31. Planned order release for Z for period 4 = 1500

32. Planned order release for Z for period 5 = 0

33. Planned order release for Z for period 6 = 1500

34. Planned order release for Z for period 7=0

35. Planned order release for Z for period 8=0

Explanation / Answer

24.) Which of the following periods have planned gross requirements for Z? Check all that apply.

Period 1

Period 2

Period 3

Period 4

Period 5

Period 6

Period 7

Period 8

25.) Which of the following periods have planned order releases of Z? Check all that apply.

Period 1

Period 2

Period 3

Period 4

Period 5

Period 6

Period 7

Period 8

26.) What is the projected on-hand at the beginning of period 1 for Z?

27.) What is the projected on-hand at the end of period 8 for Z?

28.) What is the planned order release for Z for period 1? If there is no planned order release, enter a zero.

29.) What is the planned order release for Z for period 2? If there is no planned order release, enter a zero.

30.) What is the planned order release for Z for period 3? If there is no planned order release, enter a zero.

31.) What is the planned order release for Z for period 4? If there is no planned order release, enter a zero.

32.) What is the planned order release for Z for period 5? If there is no planned order release, enter a zero.

33.) What is the planned order release for Z for period 6? If there is no planned order release, enter a zero.

34.) What is the planned order release for Z for period 7? If there is no planned order release, enter a zero.

35.) What is the planned order release for Z for period 8? If there is no planned order release, enter a zero.

Use the following inventory for the MRP problems that follow regarding Z: 4,000 800 Lot Size: On Hand: Safety Stock: Allocated: Lead Time: 0 0 0 2 4 200 800 800 Gross Requirements Scheduled Receipts Projected on Hand (Beginning) Projected on Hand (Ending) Net Requirements Planned Order Receipts Planned Order Releases 800 800 800 400 200 900 600 1500 100 800 700 1500 400 400 900 100 0 700 400 700 800 1500 200 700 1500 1500 1500