Question
Chrome File Edit View History Bookmarks People Window Help Do Homework - Abigayle Stearman tudent/PlayerHomework.aspx?homeworkld- 448250639&questionld; 18flushed-false&cld; Abigayle Stearman 12/2/17 827 PM https://wwww. tudent/PlayerHomework.aspx?homeworkld 448 Secure MGMT 626: Fall 2017 Save Homework: Chapter 14 Homework Hw Score: 67.23%, 2.69 of 4 pts 1 of 4 (4 complete) Score: 0.2 of 1 pt Question Help * %) Problem 14.8 As the production planner for Gerry Cook Products, Inc., you have been given a bill of material for a bracket that is made up of a base, 2 springs a) Design a product structure noting the quantties for each item and show the low-level coding Match each number in the structure below with and 4 clamps. The base is assembied from 2 clamps and 2 housings. Each clamp has 1 handle and 1 casting. Each housing has 2 bearings and 2 shafts. There is no inventory on hand. the corresponding item Numberm Brackct Spring) Housing Ill Casting) Base(t) Clamp(4) Clampz) b) Determine the gross quanties needed of each item if you are to assemble 150 brackets. Click the icon to view the completed product structurne Base: 150 units (onter your response as a whole number) Spring: 300 units (onter your response as a whole number). Clamp: 900 units (enter your response as a whole number) Housing: 300 units (enter your response as a whole number) Handie: 900 units (enter your response as a whole number. Casting: 900 units (enter your response as a whole number). Bearing: 600 units (onter your response as a whole number). Shaft 600 units (enter your response as a whole number) c) Compute the net quantities needed i& there are 30 of the base and 100 of the clamp in stock Base: units (entoryour response as a whole number. Spring: units (enter your response as a whole number) Enter your answer in the edit fields and then click Check Answer All parts showing Clear All Check AnswerExplanation / Answer
Net requirement = Gross requirement - Inventory
Gross requirement of Base = 150, Net requirement = 150-30 = 120
Gross requirement of Spring = 2*Net requirement of Base = 2*150 = 300
Net requirement of Spring = 300-0 = 300
Net requirement of Clamp = 2*Net requirement of Base + 4*150 - 100 = 2*120 + 500 = 740
Net requirement of Housing = 2*Net requirement of Base = 2*120 =240
Net requirement of Handle = 1*Net requirement of clamp - 1*740 = 740
Net requirement of casting = 1*Net requirement of clamp - 1*740 = 740
Net requirement of bearing = 2*Net requirement of housing = 2*240 = 480
Net requirement of shaft = 2*Net requirement of housing = 2*240 = 480