Question 1 5 pts (TCO 1) Which document is created during the initiation phase o
ID: 3756354 • Letter: Q
Question
Question 1
5 pts
(TCO 1) Which document is created during the initiation phase of a project?
The scope
The project schedule
The project charter
The project communication plan
Question 2
5 pts
(TCO 1) Projects have specific attributes. Which of the following is not an attribute of a project?
It is an ongoing endeavor.
It has a defined objective.
It requires resources.
It has a defined start and stop.
Question 3
5 pts
(TCO 2) Which step of the project life cycle defines the project scope?
Initiation
Planning
Execution
Close out
Question 4
5 pts
(TCO 2) Which statement is an example of a project constraint?
“If the parts arrive late, we will not finish on time.”
“We must get permits before we start work.”
“I believe the contracts will be signed by the 15th.”
“The paving of the parking lot is a major piece of work for this project.”
Question 5
5 pts
(TCO 3) The critical path in a project describes which of the following?
The path containing the most important pieces of work
The longest path in a project
The activities with the highest risk
The activities with the highest cost to the project
Question 6
5 pts
(TCO 3) What values are calculated on the backward pass of a project network?
Early start; late start
Early start; early finish
Late start; late finish
Early finish; late finish
Question 7
5 pts
(TCO 5) In which process of risk management are proactive and reactive strategies considered?
Plan risk management
Plan risk responses
Control risks
Qualitative risk analysis
Question 8
5 pts
(TCO 5) A risk matrix is used to _____. A risk register is a _____.
prioritize risks; list of risks
identify risks; way to categorize risks
create risk strategies; way to monitor negative risks
simulate project risks; way to categorize risks
Explanation / Answer
Ans1: The project charter
Ans2: It is an ongoing endeavor
Ans3: Planning
Ans4: “We must get permits before we start work.”
Ans5: The longest path in a project
Ans6: Late start; late finish
Ans7: Plan risk response
Ans8: prioritize risks; list of risks
Related Questions
drjack9650@gmail.com
Navigate
Integrity-first tutoring: explanations and feedback only — we do not complete graded work. Learn more.