Question 1 5 pts (TCO 1) Which document is created during the initiation phase o

ID: 3756354 • Letter: Q

Question

Question 1
5 pts
(TCO 1) Which document is created during the initiation phase of a project?

The scope

The project schedule

The project charter

The project communication plan



Question 2
5 pts
(TCO 1) Projects have specific attributes. Which of the following is not an attribute of a project?

It is an ongoing endeavor.

It has a defined objective.

It requires resources.

It has a defined start and stop.



Question 3
5 pts
(TCO 2) Which step of the project life cycle defines the project scope?

Initiation

Planning

Execution

Close out



Question 4
5 pts
(TCO 2) Which statement is an example of a project constraint?

“If the parts arrive late, we will not finish on time.”

“We must get permits before we start work.”

“I believe the contracts will be signed by the 15th.”

“The paving of the parking lot is a major piece of work for this project.”


Question 5
5 pts
(TCO 3) The critical path in a project describes which of the following?

The path containing the most important pieces of work

The longest path in a project

The activities with the highest risk

The activities with the highest cost to the project



Question 6
5 pts
(TCO 3) What values are calculated on the backward pass of a project network?

Early start; late start

Early start; early finish

Late start; late finish

Early finish; late finish



Question 7
5 pts
(TCO 5) In which process of risk management are proactive and reactive strategies considered?

Plan risk management

Plan risk responses

Control risks

Qualitative risk analysis



Question 8
5 pts
(TCO 5) A risk matrix is used to _____. A risk register is a _____.

prioritize risks; list of risks

identify risks; way to categorize risks

create risk strategies; way to monitor negative risks

simulate project risks; way to categorize risks

Explanation / Answer

Ans1: The project charter

Ans2: It is an ongoing endeavor

Ans3: Planning

Ans4: “We must get permits before we start work.”

Ans5: The longest path in a project

Ans6: Late start; late finish

Ans7: Plan risk response

Ans8: prioritize risks; list of risks