Question 29 Which of the following is not a Step in the Life Cycle of a Program?
ID: 376103 • Letter: Q
Question
Question 29 Which of the following is not a Step in the Life Cycle of a Program? a. Delivery of Program Benefits b. Defining the Program c. Managing Projects d. Program Closure Question 30 Which of the following is an element of a Program Charter? a. Assumptions and Constraints b. Program requirements c. Preparation of a network diagram d. d. a and b only Part II: Question 31 The dimensions of Project Integration Management include: a. The people dimension b. The process and procedures dimension c. The knowledge dimension d. All of the above Question 32 All of the following are examples of delivery approaches with the exception of a. Design Build b. Cost Contingency Model c. Construction manager at risk d. Build Operate Transfer (BOT)Explanation / Answer
29) A
The delivery of program benefits is outside the purview of Life cycle of a Program
30) D
The assumption, constraints and program requirements detail are part of Program charter
31) D
The integration should include all the dimensions like people, process & procedure and knowledge for coordination
32) C
Construction manager at risk is not a model for delivery. Design build, Cost contingency and BOT are models for delivery
Related Questions
Hire Me For All Your Tutoring Needs
Integrity-first tutoring: clear explanations, guidance, and feedback.
Drop an Email at
drjack9650@gmail.com
drjack9650@gmail.com
Navigate
Integrity-first tutoring: explanations and feedback only — we do not complete graded work. Learn more.