Academic Integrity: tutoring, explanations, and feedback — we don’t complete graded work or submit on a student’s behalf.

In the following MRP planning schedule for Item J, indicate the correct net requ

ID: 377650 • Letter: I

Question

In the following MRP planning schedule for Item J, indicate the correct net requirements, planned order receipts, and planned order releases to meet the gross requirements. Lead time is one week. (Leave no cells blank - be certain to enter "O" wherever required.) WEEK NUMBER ITEM J Gross requirements On-hand 73 55 74 43 et requirements Planned order receipt Planned order release erio Gross requirements Scheduled receipts Projected available balance Net requirements Planned order receipts Planned order releases 73 74 ltemJ LT= 1

Explanation / Answer

The filled up MRP table is presented below for your reference please :

Period

Item : J , LT = 1, Q = L4L

1

2

3

4

5

Gross requirement

0

73

0

55

74

Scheduled receipts

0

0

0

0

0

Projected on hand:43

43

0

0

0

0

Net requirement

0

30

0

55

74

Planned order receipt

0

30

0

55

74

Planned order release

30

0

55

74

0

Period

Item : J , LT = 1, Q = L4L

1

2

3

4

5

Gross requirement

0

73

0

55

74

Scheduled receipts

0

0

0

0

0

Projected on hand:43

43

0

0

0

0

Net requirement

0

30

0

55

74

Planned order receipt

0

30

0

55

74

Planned order release

30

0

55

74

0

Hire Me For All Your Tutoring Needs
Integrity-first tutoring: clear explanations, guidance, and feedback.
Drop an Email at
drjack9650@gmail.com
Chat Now And Get Quote