In the following MRP planning schedule for Item J, indicate the correct net requ
ID: 422751 • Letter: I
Question
In the following MRP planning schedule for Item J, indicate the correct net requirements, planned order receipts, and planned order releases to meet the gross requirements. Lead time is one week. (Leave no cells blank - be certain to enter "0" wherever required.)
WEEK NUMBER
References
In the following MRP planning schedule for Item J, indicate the correct net requirements, planned order receipts, and planned order releases to meet the gross requirements. Lead time is one week. (Leave no cells blank - be certain to enter "0" wherever required.)
Explanation / Answer
Following data are provided :
On hand quantity ( OH ) = 43
Lead time = 1 week
Following to be noted :
Net requirement for period t > Gross requirement for period t – Projected available balance for period t-1
Please refer below table for relevant data derived as per above explanations :
Period
1
2
3
4
5
Gross requirement
0
73
0
55
74
Scheduled receipts
0
0
0
0
0
Projected available balance ( On hand = 43)
43
0
0
0
0
Net requirement
0
30
0
55
74
Planned order receipt
0
30
0
55
74
Planned order release
30
0
55
74
0
Period
1
2
3
4
5
Gross requirement
0
73
0
55
74
Scheduled receipts
0
0
0
0
0
Projected available balance ( On hand = 43)
43
0
0
0
0
Net requirement
0
30
0
55
74
Planned order receipt
0
30
0
55
74
Planned order release
30
0
55
74
0
Related Questions
drjack9650@gmail.com
Navigate
Integrity-first tutoring: explanations and feedback only — we do not complete graded work. Learn more.