In the following MRP planning schedule for Item J, indicate the correct net requ

ID: 423899 • Letter: I

Question

In the following MRP planning schedule for Item J, indicate the correct net requirements, planned order receipts, and planned order releases to meet the gross requirements. Lead time is one week. (Leave no cells blank - be certain to enter "0" wherever required.)

WEEK NUMBER

In the following MRP planning schedule for Item J, indicate the correct net requirements, planned order receipts, and planned order releases to meet the gross requirements. Lead time is one week. (Leave no cells blank - be certain to enter "0" wherever required.)

Explanation / Answer

Following data are provided :

Ordering pattern = Lot for Lot ( L4L)

On hand quantity ( OH ) = 36

Lead time = 1 week

Following to be noted :

Net requirement for period t > Gross requirement for period t – Projected available balance for period t-1

Please refer below table for relevant data derived as per above explanations :

Period

1

2

3

4

5

Gross requirement

0

70

0

46

69

Scheduled receipts

0

0

0

0

0

Projected available balance ( On hand = 36)

36

0

0

0

0

Net requirement

0

34

0

46

69

Planned order receipt

0

34

0

46

69

Planned order release

34

0

46

69

0

Period

1

2

3

4

5

Gross requirement

0

70

0

46

69

Scheduled receipts

0

0

0

0

0

Projected available balance ( On hand = 36)

36

0

0

0

0

Net requirement

0

34

0

46

69

Planned order receipt

0

34

0

46

69

Planned order release

34

0

46

69

0