In the following MRP planning schedule for Item J, indicate the correct net requ

ID: 461633 • Letter: I

Question

In the following MRP planning schedule for Item J, indicate the correct net requirements, planned order receipts, and planned order releases to meet the gross requirements. Lead time is one week. (Leave no cells blank - be certain to enter "0" wherever required.)

Item J

Period 1 2 3 4 5 Gross Requirements 70 46 69

Item J

Scheduled receipts LT = 1 Projected available balance Q=L4L Net requirememts Planned order receipts Planned order releases WEEK NUMBER ITEM J Gross requirements On-hand Net requirements Planned order receipt Planned order release 5 46 69 70 36

Explanation / Answer

Period 0 1 2 3 4 5 Gross Requirements 0 70 0 46 69 Scheduled Receipts 0 0 0 0 0 Projected on Hand 36 36 36 0 0 0 Net Requirements 0 34 0 46 69 Planned Order Receipts 0 34 0 46 69 Planned Order Releases 34 0 46 69 0