In the following MRP planning schedule for Item J, indicate the correct net requ
ID: 2748524 • Letter: I
Question
In the following MRP planning schedule for Item J, indicate the correct net requirements, planned order receipts, and planned order releases to meet the gross requirements. Lead time is one week. (Leave no cells blank - be certain to enter "0" wherever required.)
WEEK NUMBER
In the following MRP planning schedule for Item J, indicate the correct net requirements, planned order receipts, and planned order releases to meet the gross requirements. Lead time is one week. (Leave no cells blank - be certain to enter "0" wherever required.)
Explanation / Answer
Projected On Hand Calculation = Last Period Closing + Scheduled Receipt + Planned Receipt - Gross Requirement Net Requirement = Last Period Closing + Scheduled Receipt - Gross Requirement (If the above calculation results in negative amount, then such amount is taken as Net Requirement, else 0) Planned Receipt = If Net Requirement > 0, Planned Receipt as per Lot Size Planned Order Release = If Planned Receipt >0, Order as per Lead Time to be placed, Here 1 week before Item = J L4L LT : 1 week Period 0 1 2 3 4 5 Gross Requirement 0 76 0 56 73 Scheduled Receipts 0 0 0 0 0 Projected On Hand 41 41 0 0 0 0 Net Requirements 0 35 0 56 73 Planned Receipts 0 35 0 56 73 Planned Order Release 35 0 56 73 0
Related Questions
drjack9650@gmail.com
Navigate
Integrity-first tutoring: explanations and feedback only — we do not complete graded work. Learn more.