In the following MRP planning schedule for ltem J, indicate the correct net requ

ID: 331495 • Letter: I

Question

In the following MRP planning schedule for ltem J, indicate the correct net requirements, planned order receipts, and planned order releases to meet the gross requirements. Lead time is one week. (Leave no cells blank - be certain to enter "O" wherever required.) WEEK NUMBER ITEM J Gross requirements On-hand Net requirements Planned order receipt Planned order release 52 75 47 Hint: enter "O" for "Scheduled receipts". Period 2 4 52 Gross requirements Scheduled receipts Projected available balance Net requirements Planned order receipts Planned order releases 75

Explanation / Answer

Solution :

J, LT - 1, Lot - L4L On Hand 1 2 3 4 5 Gross Requirements 0 77 0 52 75 Scheduled Receipts 0 0 0 0 0 Projected On Hand 47 47 0 0 0 0 Net requirements 0 30 0 52 75 Planned order receipts 0 30 0 52 75 Planned order releases 30 0 52 75 0
Hire Me For All Your Tutoring Needs
Integrity-first tutoring: clear explanations, guidance, and feedback.
Drop an Email at
drjack9650@gmail.com
Chat Now And Get Quote