8. One item a computer store sells is supplied by a vendor who handles only that
ID: 378968 • Letter: 8
Question
8.
One item a computer store sells is supplied by a vendor who handles only that item. Demand for that item recently changed, and the store manager must determine when to replenish it. The manager wants a probability of at least 96 percent of not having a stockout during lead time. The manager expects demand to average a dozen units a day and have a standard deviation of two units a day. Lead time is variable, averaging four days with a standard deviation of one day. Assume normality and that seasonality is not a factor. What is the reorder point to achieve the desired service level? (round to 2 decimal places)
Select one:
a. 55.00
b. 70.26
c. 55.04
d. None of the listed
e. 70.14
Explanation / Answer
At SL>=96%, Z = 1.76
d = 12 and LT = 4
standard deviation of demand = 2 units a day
ROP = d*LT+Z*[(LT*standard deviation of demand^2 + (d^2*standard deviation of lead time^2)]^0.5
= 12*4 + 1.76*[4*2^2 + (12^2 * 1^2)]^0.5
= 48+1.76*[4*4 + 144*1]^0.5
= 48+1.76*12.65
= 48+22.26
= 70.26
Hence the answer is option "b" i.e. 70.26