arquestenneodsto: × My Courses C Secure https.//blackboard wichita eda/w sment/take/launchjsp course assessment id 63367 1Bcourse 7444_1&step-null; a hilo you must upload your twer here Reter to the folowing table Activity Predecessor Normal TimeNormal Cost Crash Time Crash Slope 30 T0 110 F C 200 FG,H 2 Note Crash time indicales the time t could be crashed to le g A could be crashed to 3 units bud not less than that) Whle tyng to crash progecdt duration an indermediate step had the ollowing activity durations Actviy me A 4 Based on te above information, lind the activitylactiviles) that will be selected next after this intermediate step hat were reduced in terms of ther durations) Atach Fle in addtion, ind the crash time (mnmum projact duration) and coresponding cost (hiet contnue he crash time QUESTION7 2 points Oue of the FMEA tables show the values for RPN, SEV, and OCC as 20, 1, and 2 respectively Based on this inforsation, the probably to detect the failure occureace is:Explanation / Answer
Following activities have been reduced so far and by the time duration as written in parenthesis:
B(2), D(1), E(1), H(1)
Now there are three critical path in the project. These paths and their resp. duration written in parenthesis are:
A-C-F-I (12), B-D-G-I (12), B-E-H-I (12)
Activities that can be crashed now and their remaining crash times are: A (1), D (1), E (2), F (3), G (1)
We need to crash an activity on all three of these paths to reduce project duration further. The least cost to do so is by crashing activities: A, D, E
Cost of crashing these activites by 1 time unit = 10+20+50 = 80
Next we need to crash activities E, F, G. Cost = 50+200+30 = 280
Now critical path B-E-H-I is fully crashed. So project duration cannot be reduced further.
Now project duration is 10 time units. All three paths are still critical.
Total cost of project = normal cost (680) + crash cost (10+70*2+20*2+50*3+200*1+30*1+40*1)
= 1290