No programming language required.Can you assist me with answering this questionA company has taken a contract for landscaping a plot of land. The job would require workers, supervisors, excavators, tractors and a variety of trees, bushes, and shrubs beside stones in various colors and shapes. In order to simplify the matter, we presume that only labor would be required.
Details are given in the table below about activities, duration and labor requirement. Each day, 6 workers are available to finish-up the activities. Prepare a table/spreadsheet for the resource loading technique for each activity by days.
Activity Days Workers Required Precedent
A 2 6
B 5 13
C 1 3 A
D 4 8 A
E 2 6 B, C
F 6 13 B, C
G 2 5 B, C
A company has taken a contract for landscaping a plot of land. The job would require workers, supervisors, excavators, tractors and a variety of trees, bushes, and shrubs beside stones in various colors and shapes. In order to simplify the matter, we presume that only labor would be required.
Details are given in the table below about activities, duration and labor requirement. Each day, 6 workers are available to finish-up the activities. Prepare a table/spreadsheet for the resource loading technique for each activity by days.
Activity Days Workers Required Precedent A 2 6 B 5 13 C 1 3 A D 4 8 A E 2 6 B, C F 6 13 B, C G 2 5 B, CExplanation / Answer
Here , in one day only 6 workers are available, so i have created a table for each day. and activities performed,
Total no. of days taken to complete all the activities is 10.