The activities described by the following table are given for the Howard Corpora
ID: 383835 • Letter: T
Question
The activities described by the following table are given for the Howard Corporation in Kansas:
Activity
Time
(in weeks)
Immediate Predecessor(s)
Activity
Time
(in weeks)
ImmediatePredecessor(s)
Activity
Time
(in weeks)
Immediate Predecessor(s)
A
1010
minus
D
88
B
G
66
E, F
B
88
A
E
77
B
H
77
D
C
66
A
F
1010
C
I
44
G, H
This exercise contains only parts b and c.
b) The activities on the critical path are
.
c) The total project completion time for Howard Corporation is
nothing
weeks
Activity
Time
(in weeks)
Immediate Predecessor(s)
Activity
Time
(in weeks)
ImmediatePredecessor(s)
Activity
Time
(in weeks)
Immediate Predecessor(s)
A
1010
minus
D
88
B
G
66
E, F
B
88
A
E
77
B
H
77
D
C
66
A
F
1010
C
I
44
G, H
Explanation / Answer
b) The various paths and their expected completion time for this project are
So the critical path is A-B-D-H-I as it has the longest expected completion time. The activities in the critical path are A, B, D, H, I.
b) project completion time = expected completion time of the critical path = 37 weeks