Q27. Current good practice in assessing the capabilities of teams and organizations contains a strong element of self-assessment. a. true b. false Q28. If BCWP = $600, BCWS = $500, and ACWP = $900, what is schedule variance? a. -$300 b. -$100 c. $100 d. $300 Q29. On well-managed programs, the operations and maintenance phase of the program life cycle usually: a. is a large portion of the total effort b. is a small portion of the total effort c. entails heavy design work d. entails heavy development work Q30. On major programs, it makes sense for both buyer and contractor to maintain CCBs. a. true b. false

Explanation / Answer

Answer:-

27) a) True

Team Self-Assessment. This is a structured process designed for teams to explore the way they work together

28) c) $ 100

Schedule Variance (SV) = BCWP - BCWS.($600-$500)=$100

29) a)  Is a large portion of the total effort

Most effort is spent during the operations and maintenance phase

30) a) True

Change control board (CCB)are responsible for making the ultimate decision as to when and if any particular changes are to be made in regards to work products or schedule events