You work for a large manufacturing plant. Your firm is thinking of initiating a
ID: 3852490 • Letter: Y
Question
You work for a large manufacturing plant. Your firm is thinking of initiating a new project to release an overseas product line. This is the company's first experience in the overseas market, and it wants to make a big splash with the introduction of this product. The project entails producing your product in a concentrated formula and packaging it in smaller containers than the U.S. product uses. A new machine is needed in order to mix the first set of ingredients in the concentrated formula. Which of the following actions is the next best step the project manager should take?
Explanation / Answer
The following actions is the next best step the project manager should take
The project manager should document the project’s high-level requirements in a project charter document and recommend that the project proceed.
The project manager should document the key stakeholders and their potential impacts in the stakeholder register.
Related Questions
drjack9650@gmail.com
Navigate
Integrity-first tutoring: explanations and feedback only — we do not complete graded work. Learn more.