An assembly line with 17 tasks is to be balanced. The longest task is 2.4 minute
ID: 386750 • Letter: A
Question
An assembly line with 17 tasks is to be balanced. The longest task is 2.4 minutes, and the total time for all tasks is 18 minutes. The line will operate for 450 minutes per day a. What are the minimum and maximum cycle times? (Round your answers to 1 decimal place.) Minimum cycle time minutes Maximum cycle time 18 minutes b. What range of daily output is theoretically possible for the line? (Round your answers to 1 decimal place. Enter the smaller value in the first box and the larger value in the second box.) Range of output 187.5 to 25 units/day c. What is the minimum number of workstations needed if the maximum output rate is to be sought? Round up your answer to the next whole number.) Minimum number of workstations d. What cycle time will provide an output rate of 125 units per day? (Round your answer to 1 decimal 8 place.) Cycle time e. What output potential will result if the cycle time is (1) 9 minutes? (2) 15 minutes? 4 min/cycle Cycle Time Potential Output 50 units 30 unitsExplanation / Answer
CT T T/CT Ans A,B Time available Output m Min cycle time 2.4 450 187.5 M Max cycle time 18 450 25 (M/m) Min no of workstations 7.5 8 Ans C 25.0 to 187.5 Ans B D Output = Time available/Cycle time Output 125 Time available 450 Cycle time = Time available/Output 3.6 Ans D
Related Questions
Hire Me For All Your Tutoring Needs
Integrity-first tutoring: clear explanations, guidance, and feedback.
Drop an Email at
drjack9650@gmail.com
drjack9650@gmail.com
Navigate
Integrity-first tutoring: explanations and feedback only — we do not complete graded work. Learn more.